How do you ensure quality control on site?
How regularly would you inspect a job on site?
At least once a week but frequency will depend on key stages of the programme
What information do you log when visiting site?
How long would you need to keep the records of site visits for?
Records of site visits should be kept for a minimum of 6 or 12 years, depending on how the contract was executed, however negligence claims can be made up to 15 years after work was undertaken, so may need to keep for longer
What do you do if you are not satisfied with the works on site?
Who bears the cost for works that have to be opened up/uncovered for inspection?
Cost for opening up and making good is borne by the Contractor unless no defect is discovered
What standard procedural methodologies could be used to deliver a construction project?
???
Apart from hitting the completion date, does a contractor have to follow the construction programme?
???
What can you do if a contractor does not finish on time?
Client can claim LADs
What are project deliverables?
Tangible/intangible objects produced as a result of the project that are intended to be delivered to the client (e.g. a part of the site in section completion/partial possession)
What are project milestones?
Specific points along a project timeline that signal how the project is advancing
How would you determine the critical path on a construction programme?
???
Define the term ‘critical path’.
The sequence of critical tasks upon which the overall duration of the project is dependant
Define the term ‘float’.
The ‘spare’ time available in which an activity can be delayed without it impacting the critical path
What is a Gantt Chart?
In a phased project, what are the knock-on effects if the first phase is delayed?
In phased projects, any delays can have knock-on effects to the overall completion date unless there is sufficient float to make up for the delays without affecting the critical path
What contractual status does a contractor’s programme have under the major standard forms of construction contract?
What would you normally find on a pre-start meeting agenda?
What would you normally find on a progress meeting agenda?
What would you do if there was a conflict of design information on site?
What would you look for when assessing the quality of the construction of a new wall?