1 Flashcards

(133 cards)

1
Q

An engine – driven generator is used for secondary power on fire alarm systems. Of the responses below which are requirements for the battery and charger for the generator select all that apply.
A . Separate battery.
B. Automatic charger.
C. Explosion proof charger.
D. Weatherproof battery.

A

A
B
C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

EMT must be securely fastened at least _ ft from a box or terminal
A.2
B.3
C.6
D.10

A

B.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

You will achieve the highest chances of test success by learning and understanding, fire tech training, material rather than attempting to memorize sample quiz questions

A. True
B.False

A

A.True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

All communication and transmission channels between the proprieties of supervising station and a protected premises control unit shall be operated manually or automatically at least
A. Once per shift.
B. Every 12 hours.
C. Every hour.
D. Every 24 hours.

A

D. Every 24 hours.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The perimeter of canopies, loading docks and other open wall structures as indicated on drawings by
A. Single lines.
B. Double line.
C. solid lines
D. Broken lines.

A

D. Broken lines

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The main purpose of elevator recall is to disable the elevators and force occupants to use the stairways
A. True.
B . False

A

B. false. 

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

It is important to know what the system sequence of events should be known when the system is not operating as it should
A. True.
B. False.

A

A.True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Preliminary drawings led to working drawings which detail finished
A. True.
B. False.

A

A. True.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The travel distance from any point a protected area to the nearest fire extinguisher shall not exceed/FT
A. 50.
B. 75.
C. 100.
D. 200.

A

C. 100

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

You should take some time to write notes to yourself to keep track of any special condition or special requirements for an area required heat/smoke detectors
A. True.
B. False.

A

A.True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Detailed drawings, including, which of the following?
A. Land CONTOURS.
B. All non-– load bearing details of structure.
C. Plumbing system.
D. Fire alarm control panel location.

A

B. All non-loaded bearing details of structure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A heat detector in an elevator hoistway must have a setting - the operating point of a sprinkler head
A. Higher than.
B. Lower than.
C. The same as.

A

B. Lower than.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What section of the NFPA 72 defines requirements for the minimum secondary power supply capacity for Central Station service alarm systems, and equipment?
A. Section 26.3.4.7.
B. Section 10.6.7.2.5.
C. Section 10.4.2.1.
D. Section 26.6.4.3.

A

B. Section 10.6.7.2.5.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When there are multiple autonomous control units controlling the same-only one shall be in control at any given time
A. Singling line circuit.
B. Class N network system.
C. initiating device circuit.
D. Notification of appliance network.

A

C. initiating device circuit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

After locating a space spot type smoke detector within 36 inches of the top of the slope in an area with a shed type slope ceiling you must the space any additional smoke detectors by measuring up the slope of the ceiling to ensure a code compliant installation.
A. True.
B. False.

A

B. False.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A signal from a carbon monoxide alarm is permitted to have priority over a fire alarm signal
A. True
B. False.

A

B. False.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Protective gloves are worn
A. To ensure avoidance of any hand injury.
B. When working with metal stampings where there are sharp edges or splinters involved
C. When dealing with elevated temperatures of materials or equipment
D. To keep your hands clean.

A

All

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

A non-required system has been requested by a building owner since the system is not required by local court or ordinance. It is not required to meet the same requirements as required protective premises parlor system.
A. True.
B. False.

A

B.false

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

When the contract needs clarification, correction or change, this is called a
A. Allowance.
B. Addendum
C. Alternate
D. Cost plus format.
E. Fix free format.

A

B. Addendum.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Based on elevation drawing above, what is the average height of the slope? 12ft 40ft18ft [_/
A. 18 feet.
B. 12 feet.
C. 40 feet.
D. 15 feet.

A

D. 15 feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What drawings would be used to locate a smoke detector by the fire protection engineer in an area?
A. Mechanical drawings
B. Riser drawings.
C. Elevation drawings
D. Reflect the ceiling plans.

A

D. Reflected ceiling plans.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Control unit diagrams shall include, which of the following information
A. All indicators and manual control.
B. Identification of control equipment depicted.
C. All circuits connected to wiring terminals.
D. Field connections to an elevator shop trip circuit.

A

All

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What information about the layout should know or research prior to starting heat detector layout (select all all that apply )
A. Location of domestic water main
B. Expected ambient temperature for the area.
C. Building electrical load calculations.
D. Expecting maximum ceiling temperature.
E. Location of instructions on the ceiling.
F. Location of movable walls if any 

A

B D E F

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

The owner of a building wants to have a sprinkler system installed in a new addition he has asked the general contractor to include the sprinkler contractor in his contract. The sprinkler contractor will become.-contractor to the general contractor

A. Prime.
B. Sub.
C. Main.
D. Second tier.

A

B. Sub.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Which of the following should you console prior to beginning detective layouts? A. Building code. B. Scale floorplans. C. Building site plan. D. Scaled ceiling plan. E. Manufacturers equipment, data sheet. F. Organizational structure of the owners team.
A B C D E F
26
On a smooth ceiling with the height of 26.25 what will be the spacing for heat detector with the manufacturers listed placing of 30 feet A. 6 feet B. 12 feet. C. 18 feet. D. 21 feet.
B.12
26
Calculate the minimum amp our batteries for the following fire alarm system Control unit 1 each .1 amp standby .5 A in alarm Smoke detectors 10 each .00002 A standby .00005 A in alarm Horns strobes five each .0 A standby .050 A an alarm The system was operate for 36 hours in standby and at the end of the period it must be capable of operating an alarm for 10 minutes. Perform better calculations and choose the minimum size batteries permitted the scenario. A. Three amp hours. B. Four amp hours. C. five amp hours D. Six amp hours.
C . Five amps
27
When space and spot type heat detectors in an area with a shed type slope ceiling, you must base the detectors of the slope of the ceiling to ensure a code compliant installation A. True. B. False.
B.False
28
Add determination of a project or at a point of substantial completion-are prepared A. Site planning drawing. B. Mechanical drawings. C. Working drawings. D. As built drawings.
D. As built drawings.
29
An auxiliary relay to shut down the HVAC system from the fire alarm, control panel must be located within= feet of the HVAC system A. 20. B. 15. C. 10. D. 3.
D.3
30
You should visually inspect all PPE and safety equipment A. Week B. Monthly. C. Each shift. D. Before every use.
D. before each use.
31
On this other way, permitted by code, evacuation messages shall be proceeded and followed by a minimum= the emergency evacuation signal A. One cycle. B. Two cycles C. One tone. D. Two toes.
B. Two cycles.
32
Which of the following documentation is the owner not required to provide the contractor prior to system testing A. Record of completion. B. Floorplan. C. wiring diagrams D. Operation manual. E. None are required. F. All required.
F.
33
Which box below would be suitable for the following conductors 4 12 AWG conductors 4 16 AWG conductors Five equipment grounding conductors 4 16 AWG unbroken not place passing through the box A. 4–11/16.x 1–1/4 square box B. 4–11/16x 1–1/2 square box C.4x1–1/2 square box D.4x 2–1/8 round box
B.
34
Failure of a device during automatic testing shall result in a= signal A. Visual trouble. B. Visual and audible trouble. C. Visual supervisory D. Visual and audible supervisory.
B. Visual and audible trouble.
35
Which of the following is true regarding operation of class a radio pathways in a protected premises fire alarm system A. Every redundant pathway is not required. B. Operational capacity is verified using end to end communication. C. Each receiver or repeater is powered by a primary power source only. D. None of the above.
B. Operational capability is verified using end to end in communication
36
When a DACR is used spare equipment must be maintained and the supervising station or subsidiary station and what timeframe must the spare DACR be online after the detection of a failed unit A. 30 seconds. B. Four minutes. C. Two minutes. D. 60 minutes.
A. 30 seconds.
37
What are the parts of the basic contract package?(Select) A. The contract itself. B. Contract conditions C. Specifications. D. Project drawings.
All
38
A respirator is a device which removes solid particles from the air, such as dust, mold, bacteria, and pollen A. True. B. False.
B.false
39
When a software change is made to a fire alert system what percent of the ignition devices does not affect the change must be tested A. Zero. B. 10%. C. 20% D. 100%.
C.20%
40
An exhaust fan on the roof of the protected premises is used as part of the smoke control system that firearm control panel is located on the bottom floor. The motor started for the fan is in the 10th floor electrical room. The exhaust fan is on the roof, the 10 story building the interface the device must be located within.= of the= A. 3 feet of the fire control panel. B. 3 feet of the roof fan. C. 3 feet of the fan motor starter. D. 3 feet of the control panel roof fan or the fan motor starter.
C. 3 feet of a fan motor starter.
41
A reflected ceiling plan is likely to show which of the following A. Sprinkler heads. B. Light fixtures. C. light switch switches D. Stairways. E. Fire alarm pull stations. F. Steel beams.
A B C E F
42
Notification appliance circuit may be designated as which of the following responsibility below A. Class A B. Class B. C. Class C. D. Class d E. Class E. F. Class n G. Class X.
A B D F G
43
On a ceiling or beam project less than 12 inches below the ceiling and the beans are less than 8 feet on the center. Heat detector shall be installed on the bottom of the beams A. True. B. False.
B. False.
44
Select all of the below technologies that are permitted for the use of fire alarm system signaling pathways A. Wireless. B. Copper wiring. C. Ethernet D. Fiber optic.
All
45
Which of the following is true when using an aerial lift A. Tie off with a lanyard B. Hard hats must be worn. C. Training is required before operating. D. If reach is not sufficient, use the platform on the lift.
A B C
46
Battery calculation for the secondary power supply must have=% correction factor added for aging to ensure the battery can meet is current demand at the end of service life A. 10. B. 15. C. 20. D. 25.
D. 25%
47
If we need to find resistance per foot of a#12 AWG copper conductor where would we find this information? A.NFPA 72 2022 table. 17.6.3.5.1. B. NFPA 72, 2022 table a.18.4.1.2. C. NFPA 70, 2020 table 9. D. NFPA 70,2020 table 8.
D. NFPA 70,2020 table 8.
48
A non-sprinklered group a building is required to have a manual fire alarm system if the occupant load is= or more A. 100. B. 200. C. 250. D. 300.
D.300
49
The safety data she provides, which of the following information for a chemical A. Physical and chemical properties B. Hazard identification C. Emergency and first aid procedures. D. All of the above.
D
50
NFPA 72 state stored energy power supply systems used to provide secondary power to fire run systems must be installed per the recommendations on the manufacturer and requirement of NFPA 70 A. True. B. False.
B. False.
51
Select all of the following that are required page of zones by the IBC for emergency voice alarm communication systems A. Each elevator group. B. Each side of the floor more than 10,000 feet.(squared) C. Each interior exit stairway. D. Each branch of an inside shopping mall.
A C
52
What type of cable could be used in a place of FPL in a power limited fire alarm circuit A. FPLP. B. FPLR. C. CM. D. CMG. E all of the above F. None of the above.
E
53
Safety shoes for performing electrical work must be non-conducted and slip resistant A.true B. False.
B. False.
54
Through penetrating fire stop requirements are covered in which section of the IBC A. Section 714. B. Section 906. C. Section 907. D. Section 1006.
?
55
What is the maximum amount of time a fire alarm control panel has before it must announce a trouble signal and the protected promises A. 120 seconds. B. 160 seconds. C. 180 seconds. D. 200 seconds.
D. 200 seconds.
56
To get the correct heat detective spacing for ceiling height of 14’7” the heat detector listed spacing must be multiplied by A..71. B..84. C. 0.77. D. None of the above.
C. 0.77.
57
All the supervising stations firearm systems will be programmed to report restoral signal to the supervisor station of all alarms, supervisor in trouble signs upon restoration of activation A. True. B. False.
A. True.
58
What is the maximum number of 14 gauge wires which can be pulled straight through a 4 inchX 2 1/8 in. Square trade size metal electrical box. A. Six. B. Seven. C. 10. D. 12. E. 15.
E.15
59
How close to a sidewall are we permitted to locate a ceiling mounted smoke detector A. 0 inches. B. 4 inches. C. 6 inches. D. 12 inches.
C. 6 inches.
60
Authorities, having jurisdiction must be notified within= of the expiration or cancellation of the central station service by the organization that has listed a prime contract A. 30 working days. B. 60 working days C. 30 calendar days. D. 60 calendar days.
C. 30 calendar days.
61
According to the OSHA, what is not required to have the color red as the basic color for identification A. Fire protection, equipment, and apparatus. B. Safety cans or other portable containers of flammable liquid liquids having a flashpoint at or below 80%. C. Firetrucks. D. Table containers of flammable liquid liquids. E. Light at barricades F. Danger signs. G. Buttons or electrical switches on which letters or other markings appear used for emergency, stopping a machine machinery.
C. Firetrucks.
62
In building fire, emergency voice/alarm communication systems are required to use positive alarm sequence to minimize nuisance or unwanted alarms A. True. B. False.
B.False
63
When you are doing a layout for a heat smoke detection grid where would you find the requirements for the occupancy? A. NFPA 70. B. NFPA 72. C. Building code. D. Project plans.
?
64
The raw of the architect and the design of the construction of building includes, which of the following A. Assist owner with prime contractor selection B. Approved subcontractor selections. C. Interpret drawings and resolve conflicts D. Settled dispute between contractors and subcontractors. E. Solve material delivery issues
A C
65
A location of parts supplies located remotely from the f-arm control unit must be identified at the A. Riser drawings B. Mechanical plan. C. Master control unit. D. Electrical drawings.
A. Riser drawings.
66
A non-fire emergency manual act stations must be listed to which of the following A. UL 864. B.UL 60950 C. UL 2572. D.UL 2017
D. UL 2017
67
Solid structural of solid non-structural members projecting down from ceiling, four or more inches and space of 36 inches or less are defined as A. Beam construction. B. Girder C. Smooth ceiling. D. Solid joist construction.
D. Solid joist construction.
68
When load testing above regulator lay acid battery the charge test is the first test performed A. True B. False.
B. False.
69
There are two ratios requirement performing a smoke detector layer on ceilings with beams or joist. These rather help us know which location is place requirements apply to and which should not what are these two ratios? A. Depth to ceiling height ratio. B. Rise over run ratio. C. Slope angle ratio. D. Spacing to ceiling height ratio. E. Run over rise ratio
All
70
Which box volume below would be suitable for the following conductors 2 10 AWG conductor Two 12 AWG conductors Eight 14 AWG conductors Six equipment grounding conductors For cable clamps A. 25 inch cube B. 30 in.³ C. 35 inch cube. D. All of the above.
C. 35
71
According to NFPA 72, chapter 17 is placing of the heat detector should not be required to be less than .4 times A. The heat detector is B. Heat detectors point 0.7S value. C. The ceiling height. D. The average height of the ceiling
?
72
Spotty heat detectors installed in an area with a solid joist must be mounted A. In the pocket formed by the joists B. On the bottom of the joist. C. On either of the pockets formed by the joists  or the bottom of the joists. D. none of the above.
C. On either of the pockets for by the joists or the bottom of the joist.
73
The IBC requires that at least = sleeping rooms in a transient hotel with the total of 45 rooms have visible notification appliances A. 45. B. 25. C eight D. Four.
D.4
74
On a pic or shred sloping ceiling if a ceiling has a slope for 38° all detective shall be spaced, using the average slope height, or the height of the peak A. True. B. False.
B.False
75
A 16 foot extension ladder is being used. How far from the wall or support should the base be? A. 3ft B. 4FT. C. 5FT. D. 6FT.
B. 4FT.
76
Audible alarm notification for a fire alarm system shall produce signals that are= from other similar appliances used for other purposes in the same area that are not part of the fire or emergency communication system A. Coded. B. Non-coded. C. Distinctive. D. None of the above.
C. Distinctive.
77
NNFP a handbook is an a substitute for any of the NFPA standard permitted to be brought into the exam A. True. B. False.
B.False
78
You must install a spotty heat detector in a square room with the ceiling height of 9 feet and one portion of the room there is a partition that exceeds 8 feet above the finish floor is this partition considered a wall for the purposes of heat detective locations spacing A. Yes the partition is considered a wall. B. No the partition is not considered
A
79
A building with a peak ceiling has the following measurements Height at top of slope equals 10 feet Height at bottom of slope equals 7 feet Run equals 20 feet What is the rise of the ceiling? A. 3 feet. B. 10 feet. C. 13 feet. D. 17 feet.
A. 3 feet.
80
NP 72 requires an emergency response plan to be accomplished for each new fire alarm system that is to be installed A. True. B. False.
B. False.
81
On a smooth ceiling with the height of 30 feet what will be the spacing for heat detector with the manufacturers listed placing of 25 feet A. 8.5 feet. B. 17 feet. C. 12 D. 6 feet.
?
82
When measuring a fire optic cable for optical power loss at what level reduction in power from the test cable be replaced A. 5% B. 10%. C. As specified in a NSI/TIA586.3. D. As specified in a NSI/TIA568.3.
?
83
Before any battery testing performed, the technician must A. Verify all system software stored, and non-volatile memory is protected from loss B. Verify all system software in volatile memory is protected from loss. C. Verify all system firmware stored in nonvolatile of memory is protected from loss. D. Verify our system firm stored in volatile memory is protected from loss.
B. Verify all system software in all time memory is protected from loss.
84
After modifying a fire alarm system site specific software your required device, the record of a completion of the system where in the code are the requirements for the record of completion documents found A. Section 10.4 B. Section 10.8. C. Section 7.5.6. D. Section 4.8.3
?
85
After loss of primary power primary text visual not notification places must have sufficient secondary power to operate. What is the minimum continuous display of appliances? Must operate during emergency events? A. One hour. B. Two hours. C. 12 hours. D. 24 hours.
C. 12 hours.
86
You must install spotty heat detectives on the smooth and level ceiling at a height of 30 feet if the heat detector list is placing is 50 feet. What is the maximum spacing a lot between the heat detectors and the partition extent within 15% of the ceiling height? A. 8.5 feet. B. 12 feet. C. 15.5 feet. D. 17 feet.
D.17 ft
87
Signaling line circuit may be designated as which of the following responses below A. Class a B. Class B. C. Class c D. Class D. E. Class E. F. Class N. G. Class X.
ABCFG
88
The correctly performed better calculations we must be able to convert electrical values given an equipment sheets in decimal numbers what are the decimal form of 456 mA A. 45.6 A B. 4.56 A. C. 0.456 A D. 0.0456Amps
C. 0.456 Amps
89
Periodic testing records are required to be maintained for A. One year after the next test. B. One year. C. Five years. D. The life of the system.
?
90
Interconnection mean shall be arranged so that A = does not cause an alarm system A. Short circuit or single break B. Short circuit or ground fault. C. Single break or single ground fault D. Single break or multiple ground faults.
C. Single brick or single ground faults.
91
The wiring between a fire and control unit and emergency control function and they should device must be either class A class B class D class and or class n or x per the requirements A. NFPA 72 chapter 7. B. NFPA 72 chapter 12. C. NFPA 70 chapter 3. D. NFPa 70 article 760
B. NFPA 72 chapter 12.
92
Contractor can’t work for the owner for a A. Fee. B. Time and C. Cost plus D. Firm. E. All the above.
E
93
A multiple prime contractive project is one where = contractors have a direct contract with the owner or representative? A. all B. Prime. C. Sub. D. Building.
B. Prime
94
A ceiling with a high point at one side with the slope, extending to the opposite side is called A. Sloping peak type ceiling. B. Smooth ceiling. C. Girder ceiling D.None of the above.
D.
95
If a defect is found when inspecting a firearm system that cannot be corrected at the conclusion of the system inspection the owner should be notified in writing within the what timeframe A. 24 hours. B. Immediately after the defect is found. C. Five business days D. Eight hours.
A.24 hours
96
97
Yeah, just finished troubleshooting and replacing one horn/rope on a firearm system to ensure the system operates as attended or must be done before leaving the premises A. Functionality test all the horn shows on the affected circuit and 10% initiative devices of the system up to maximum of 50. B. Functionally tested the horn/strobe you replaced and 10% ignition devices on the system up to maximum 50. C. Functionality test the horn should be replaced in 10% of remaining horn/ strobes D. Functionality test the horn/strobes you replaced.
D
98
If one or more elevator elevators are designated and marked as far as service access elevators. The elevator lobby at the designated recall level must be periodically monitored for temperatures. A. True. B. False.
B. False.
99
Selected revise that required lockout to control energy A. Circuit breaker. B. Switch. C. Valve. D. Block.
A B
100
If the air will change in the area every six minutes, what will be the maximum space in between any two smoke detectors located in the area? A. 28.73 feet. B. 23.78.feet C. 27.38 feet. D. 28.37 feet.
B.23.78 ft
101
When a public address system is interface with the facility fire system to deliver mass notification messages which features below must be provided by or added to the public address system select all the apply A. Our individual or zone speaker volume controls must be default to the emergency sound level when used for emergency mass notification messages B. Emergency messages are not required to have a priority over non-emergency messages C. The vision notification network must be provided required. D. The public address system branch circuit must be dedicated branch circuit serving no other loads.
A C
102
The secondary parts supply capacity from an emergency command center of a wide area of mass notification system must be able to supply back up power for minimum of A. 12. B. 24. C. 36. D. 48.
B. 24.
103
If required by the ahj verification of compliance installation must include, which of the following A. All required system documentation is completed as archived, but then still installing contractor the AHD and the owner of the owners representative. B. For existing supervising station system that are extended and modified or configured the location shall be required for the new work as well as as a existing system and assistance testing as accordance with chapter 14 shall be accomplished. C. For new supervise station system verification should also certain proper arrangement transmission and receipt of all signal required to be transmitted of off premises and shall meet the requirements of section 14.4.1 and 14.4.2. D. None of the above.
C
104
When you are doing a layup for a heat/smoke protection grit where would you find the requirements for the occupancy? A. NFPA 70. B. NFPA 72. C. Building code. D. Project plans
C. Building code.
105
We’re connected to a supervisor station protected premises fire alarm system, employing, automatic, fire detectors of water protection devices shall include= to initiate signal to the supervisor station A. A spot smoke detector. B. A line type heat detector. C. Disconnecting means. D. A manual alarm fire box.
A. Manual fire alarm box.
106
The safety data she provides, which of the following information for a chemical A. Physical and chemical proper. B. Hazard identification. C. Emergency and first aid procedures D. All of the above.
D
107
To find a short circuit of ground falls on the conventional fire system IDC you must A.Disconnect the primary power and secondary power for the fire alarm control unit B. Disconnect IDC you will test from the fire alarm control unit. C use a volt meter D. Use an ohm meter.
A B C
108
In building emergency mass notification operation shall be permitted to be in initiated, our operation of a handheld microphone or an automatic fire detector A. True. B. False.
A. True.
109
How close the sidewall are we permitted to locate a ceiling mount smoke detector A. 0 inches. B. 4 inches. C. 6 inches. D. 12 inches.
C. 6 inches.
110
What is the maximum amount of time a fire alarm control panel has before it must annunciate A trouble signal at the protective premises. A. 120 seconds. B. 160 seconds. C 180 seconds D. 200 seconds.
D. 200 seconds.
111
During the loss of primary power a protected premises paragon system components will draw 1.5924 A while in standby and 1.9438 A in alarm mode what size batteries must be used to enable system to operate for minimum of 48 hours in standby and at the end of the period be able to operate for at least 15 minutes an alarm at full load Perform battery calculations and choose the minimum size batteries permitted in the scenario A. 77 hours. B. 100 hours. C. 110 amp hours. D. 170 amp hours.
B. 100 amp hours.
112
A respirator is a device which removes solid particles from the air, such as dust, mold, bacteria, and pollen A. True. B. False.
B. False.
113
The assignment of class as a nation for initial devices circuits can be class A B or class X A. True. B. False.
B. False.
114
Audible alarm notification appliances for fire system shop produce signals that are= from other similar appliances used for other purposes in the same area that are not part of the fire alarm or emergency communication system A. Coded. B. Non-Coated C. Distinctive. D. None of the above.
C. Distinctive.
115
Electrically lock doors in a= shall unlocked in the direction of egress was required by other laws, codes and governing standards A. High security area. B. Required by means of egress. C. Protect the premises. D. All of the above.
B. Required by means of egress.
116
Where would you find the testing and maintenance requirements for an engine driven generator used for large system secondary power A. NP 70. B. NFPA 72. C. NFPA110. D. NFPA111.
C. NFPA110.
117
Class F fires that involve A. Flammable liquids, combustible liquids, patrolling Greece oil based paint, solvent alcohol and flammable gases B. Both of them are magnesium, titanium, sodium lithium, and pot C. Cooking appliances involve cooking media. D. Energize electrical equipment.
C.
118
What drawing would be used to locate the smoke detectors by a fire protection engineer in an area? A. Mechanical drawing. B. Riser drawings. C. Elevation drawings. D reflected ceiling plant
D. Reflected ceiling plan
119
The Proprietary supervising station shall have A.recording device B.two different ,means for alerting the operator D. All the above
D
120
When a DACR is used spirit equipment must be maintained in the supervising station or subsidiary station and what time frame must be the spare DACR be online after depiction of a failed unit A. 30 seconds. B. Four minutes. C. Two minutes. D. 60 minutes.
A.30 Seconds
121
If more than one contractor installed a fire alarm system who finally analyzes the record of completion for the system A. The owner of owners representative. B. Each contractor will complete the portions of the record that they have responsibility for. C. The prime contractor or fire alarm contractor. D. The authority having jurisdiction.
B. Each contractor will complete the portion of the record that they have responsibility for.
122
If the top of the girder for the beam ceiling are within 4 inches of the ceiling the girder= select all A. Is considered a beam. B. Is considered a joist. C. Is a factor in determining heat detector spacing D. Does not have an effect of heat detector spacing
A C
123
What type of fire extinguisher would you use for a fire where there are combustible metals such as lithium or titanium? A. class.A B. Class B. C. Class.c D. Class D.
D
124
On a 10 foot high, smooth and level ceiling a heat detector with manufactured listed spacing 40 feet will be placed no more than= from a wall or partition A. 21 feet B. 15 feet. C. 20 feet. D. 28 feet.
C.
125
What is the testing frequency for an end German generator supplying parts of a fire alarm system A. Weekly. B. Monthly. C. Semi annually. D. Annually.
B.monthly
126
During the loss of primary power of protect the premises for our system components or draw .72 A while in standby and .89 A in alarm mode what size batteries must be enabled the system to operate for minimal 24 hours of standby and at the end of the period be able to operate for at least 10 minutes alarm at full load A. 12 hours. B. 18 amp hours. C. 20 amp hours. D. 26 hours.
D.
127
What are the parts of the basic contract package? (SATA) A. The contract itself. B. Contra conditions. C. Specifications D. Project drawings
All
128
NP 72 stored energy parts supply systems used to provide secondary part to fire systems must be installed per the recommendations of manufacturer of the requirements of NFPA 70 A. True. B. False.
B.false
129
Computer ate an alarm and supervised signal processing hardware and software equipment= For the purpose A. Label. B. Listed C designated D. engineered
B.listed
130
Drawings with the architect submits with all final changes that have occurred throughout the duration of the project are called A. As built drawings. B. Working drawing. C. Preliminary drawing. D. Detailed drawings.
A.
131
He checked, was used in areas with peak ceilings shall have a row of detectors first place and located within= the peak measured horizontally A. 6 inches. B. 12 inches. C. 24 inches. D.36 inches
D.36
132
Which pathways viability level requires the use of 4 hour fire enclosure A. Level.0 B. Level one. C. Level two. D. Level three. E. Level four. F. None.
F none