Identify who normally prepares an Acquisition Strategy
Usually prepared by an Acquisition Strategy IPT, with representatives from all functional areas, as well as end users and key stakeholders
The Acquisition Strategy is due at Milestone___ and updated before______________.
A, each milestone review
What is an Acquisition Strategy?
A business and technical management approach designed to achieve program objectives within the resource constraints imposed
Describe the concept of international cooperation, as it pertains to the development of the acquisition strategy.
What provides mandatory guidance for the operation of the Defense Acquisition Management System?
the DoDI 5000.02
What are the two strategy approaches to full system capability.
* Evolutionary
____________________is the preferred strategy for rapid acquisition of mature technology.
Evolutionary acquisition
In the _______________, the ultimate capability delivered to the user is divided into two or more increments, with increasing levels of capability. Increment 1 of an evolutionary acquisition strategy provides the initial deployment capability (a usable increment of capability called for in the CDD/CPD).
Evolutionary approach
_____________ of an evolutionary acquisition strategy provides the initial deployment capability which is a ________________called for in the CDD/CPD.
* usable increment of capability
It is mandated, by law (Section 2366b of Title 10, United States Code), that _________ in a program must have been ________________ to enter Milestone ____ and be Technology Readiness Level (TRL) ____.
Identify what documents guide the MSA phase.
* AoA Study Plan
What is the Formal initiation of the program which requires demonstration that all sources of risk have been adequately mitigated and MDA approves APB as the agreement between the MDA, PM, and Component chain of command (Affordability caps set in APB as equivalent to KPPs)
Milestone B
Identify the major activities that occur during the EMD phase.
If ______prior to MS B was waived, the PM will plan for / conduct _____ as soon and feasible after program initiation
a (Preliminary Design Review) PDR, a PDR
For ACAT ID and IAM programs, the DASD(SE) will participate in the Program’s _____________and conduct the _____________
* CDR Assessment
The EMD Phase ends when:
* Industrial production capabilities are reasonably available
What is the purpose of the Full Rate Production/Deployment work effort?
Produce and deliver requirements compliant products
What is a business and technical management approach designed to achieve program objectives within the resource constraints imposed.
Acquisition Strategy
What are the disadvantages of International Cooperation?
o Requires an international agreement setting forth terms and conditions of the cooperation
o Legal and administrative requirements, including coordination with the State Department
o Possible dependency on foreign sources
o Security issues associated with technology transfer between countries
What are the advantages of International Cooperation?
o Development costs are shared
o Use of emerging or existing foreign technology,
o Potential to reduce production costs through sharing of costs and reducing unit cost by economy of scale
o Promotes interoperability with future coalition partner nations