What should you consider when recommending a form of contract?
What does a Contract need to be binding?
1) Offer
2) Acceptance
3) Consideration
4) Intent to create legal relations
What are the differences between Under Hand or Under Seal (as a Deed)?
When would you expect something to be signed Under Hand vs. Under Seal?
Explain the make up of an NEC ECC Contract
General Terms
Contractors Responsibilities
Time
Testing and Defects
Payment
Compensation Events
Title
Risk and Insurance
~~~
Can you identify all the Main NEC ECC options?
A - Priced Contract with Activity Schedule
B - Priced Contract with BoQ
C - Target Contract with Activity Schedule
D - Target Contract with BoQ
E - Cost Reimbursable Contract
F - Management Contract
When would you use Option B?
When would you use Option A?
When would you use Option C?
When would you use Option E
- Just need to get on with it
When would you use Option F
What JCT Contracts do you know of?
What is the difference between Reasonable and Best Endeavours?
Reasonable is less onerous than Best.
Best implies that no stone should be left unturned and that may mean a party has to use extra resources to do so. If they don’t, they may find themselves in breach.
What is the CE process under NEC?
Key Rules
What Insurances are required under JCT?
What Insurances are required under NEC?
NEC4 states the four specific events for which the contractor is liable. These are:
Can you tell me about design liability in NEC4?
What was the Third Party Rights Act 1999?
Reformed the principle of contract privity in English law to allow third party rights
What was the Latham Report 1994?
‘Constructing the Team’ - identified two key things:
1) Payment practices were poor
2) Disputes were expensive and time consuming.
Led to many of the elements of the Housing Grants, Construction and Regeneration Act 1996
What are the key elements of the Housing Grants Construction and Regen Act?
1996
- Right to stage/interim payments after 45 days
- Right to adjudication
- Removal of pay when paid
- Right to be informed of amounts due
- Right to suspend works
What are the key elements of the Local Democracy Economic Development Construction Act?
2009
- Withholding notice changed to Pay Less
- Contracts don’t just have to be in writing
- Payment notice still required even if zero
- Payment notice required 5 days after due date
- Remove pay when certified loophole
- Remove unfair allocation of adjudicator’s costs
What is Tort Law?
Area of law that mainly deals with negligence. Allows parties to bring a case against another due to the Duty of Care.
What are the three general types of LOI?
What are the key things to consider about LADs?