Precedence Table
A table, which shows which activities must be completed before others are started (a.k.a., dependence table)
Activity on Arc Network
The activities are represented by arcs and the completion of those activities, known as events, are shown as nodes
Dummy Activity
A dummy activity has no time or cost. Its sole purpose is to show dependencies between activities
Every activity must be ____ in terms of its events. This requires that there can be ____ between any two events
Uniquely represented, at most one activity