What is the Schematic Design phase of the project?
When the client’s requirements & desires assume architectural form.
What 3 aspects of the project are illustrated during SD?
Identify the information required for schematic design, given specific conditions. (6)**extra services?
1 - Confirmation of functional & spatial requirement and program relationship
2 - Amount of Flexibility & provision for expansion
3 - Special Equipment and System Requirements.
4 - Site Requirements
5 - Construction Budget
6- Construction schedule.
**Architect can procure these with an extra fee:
+ Legal Surveys
+ Reports (Geo, Hazards, etc.)
What consultants are typically engaged on a design team? Categorize the engineering services required for the schematic design of a given project (program, clients and context). (2)
1 - Arch to assemble design team:
Site design, Structure, Envelope, Mechanical, and Electrical
+Special sub-consultants may be required
2 - Engineers work with Arch to prepare:
2a mech/structural/electrical system concepts
2b budget at end of SD phase
What drawings and other graphic representations are typically prepared for the client during this phase? (3 types)
1 - Site Plan, Principle Floor Plans, Vertical Sections, Building Elevations.
2 - Illustrative sketches/perspectives/renders
3 - Massing Models
What is typically provided by consultants in the SD report? (2)
~ SME systems approach
~ probable construction/operating costs
Explain the scope of building code analysis in schematic design. (7)
1 - Environmental impact, Zoning, Parking Requirements and Limiting Distance. (General Overview rather than a detail analysis)
2 - Occupancy/Classification
3 - Occupancy/Compartment fire Separations
4 - Area & Occupant Load
5 - Exiting & Egress (Travel Distance and Widths for large Buildings)
6 - BF Requirements
7 - Washroom Count
Explain the principles of sustainable design as they relate to the Building (size, footprint, mass, form, and circulation) during schematic design.
Explain the principles of sustainable design as they relate to the Site (parking / topo) during schematic design.
How can the Architect foster sustainable design during schematic design.
- Identify targets: - ie LEED
What information is required during Schematic design? (2)
2. Complete information about site
What information is required for the site during Schematic design? (3)
What services are done by engineers during schematic design? (6)
Documents to prepare by architect during schematic design? (3)
What do the presentation documents show during Schematic design (2)?
What is included in the outline specifications / texte during Schematic design (8)?
What is the architect’s task during schematic design? (9)
What are optional services for architect during schematic design? (7)
What is an integrated design approach?
Advantages of integrated design approach?