5_variance_analysis Flashcards

(42 cards)

1
Q

What is Standard Costing?

A

A costing system that uses predetermined or target costs (standards) for products or services. These standards are set in advance and used as benchmarks to measure actual performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a Standard Cost?

A

A predetermined or target cost for a unit of product or service. It represents what a cost SHOULD be under efficient operating conditions. Standards are set for materials, labour, and overheads.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a Variance?

A

The difference between a standard (budgeted) cost and the actual cost incurred. Variances highlight where performance differs from expectations and require investigation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a Favourable (F) Variance?

A

A variance where actual results are BETTER than standard/budget:
- Actual costs are LOWER than standard (good)
- Actual revenue is HIGHER than standard (good)
- Actual profit is HIGHER than standard (good)
Favourable variances INCREASE profit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is an Adverse (A) Variance?

A

A variance where actual results are WORSE than standard/budget:
- Actual costs are HIGHER than standard (bad)
- Actual revenue is LOWER than standard (bad)
- Actual profit is LOWER than standard (bad)
Adverse variances DECREASE profit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is Material Price Variance (MPV)?

A

Measures the effect of paying a DIFFERENT PRICE for materials than the standard price. It isolates the impact of price changes from usage changes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Material Price Variance Formula

A

MPV = (Standard Price - Actual Price) × Actual Quantity Purchased/Used

Where:
- Standard Price = budgeted price per kg/unit
- Actual Price = actual price paid per kg/unit
- Actual Quantity = quantity purchased or used

Favourable if Standard Price > Actual Price (paid less than expected)
Adverse if Standard Price < Actual Price (paid more than expected)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Material Price Variance Example 1

A

Standard price = £5 per kg
Actual price = £4.80 per kg
Actual quantity purchased = 1,000 kg

MPV = (£5 - £4.80) × 1,000 = £0.20 × 1,000 = £200 Favourable

We paid £0.20 less per kg, saving £200 total.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Material Price Variance Example 2

A

Standard price = £8 per metre
Actual price = £8.50 per metre
Actual quantity = 2,500 metres

MPV = (£8 - £8.50) × 2,500 = -£0.50 × 2,500 = £1,250 Adverse

We paid £0.50 more per metre, costing £1,250 extra.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What causes Material Price Variance?

A

Favourable MPV:
- Bulk discounts obtained
- Cheaper suppliers found
- Lower market prices
- Effective negotiation

Adverse MPV:
- Price increases from suppliers
- Buying higher quality materials
- Urgent purchases without negotiation
- Inflation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is Material Usage Variance (MUV)?

A

Measures the effect of using MORE or LESS material than the standard quantity for the actual output achieved. It isolates the impact of efficiency/waste from price changes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Material Usage Variance Formula

A

MUV = (Standard Quantity for Actual Output - Actual Quantity Used) × Standard Price

Where:
- Standard Quantity for Actual Output = standard usage per unit × actual units produced
- Actual Quantity Used = actual material used
- Standard Price = budgeted price per unit

Favourable if Standard Quantity > Actual Quantity (used less material)
Adverse if Standard Quantity < Actual Quantity (used more material)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Material Usage Variance Example 1

A

Standard usage = 5 kg per unit, Standard price = £6 per kg
Actual production = 800 units
Actual quantity used = 3,800 kg

Standard quantity for 800 units = 5 kg × 800 = 4,000 kg
MUV = (4,000 - 3,800) × £6 = 200 kg × £6 = £1,200 Favourable

Used 200 kg less than expected, saving £1,200.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Material Usage Variance Example 2

A

Standard usage = 3 metres per unit, Standard price = £10 per metre
Actual production = 1,000 units
Actual quantity used = 3,200 metres

Standard quantity for 1,000 units = 3 metres × 1,000 = 3,000 metres
MUV = (3,000 - 3,200) × £10 = -200 metres × £10 = £2,000 Adverse

Used 200 metres more than expected, costing £2,000 extra.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What causes Material Usage Variance?

A

Favourable MUV:
- Less waste/scrap
- Better quality materials
- Skilled workers
- Efficient processes
- Better supervision

Adverse MUV:
- More waste/scrap
- Poor quality materials
- Inexperienced workers
- Machine breakdowns
- Poor supervision

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Total Material Variance Formula

A

Total Material Variance = Material Price Variance + Material Usage Variance

Or calculated directly:
Total Material Variance = (Standard Cost - Actual Cost) for actual output

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Total Material Variance Example

A

MPV = £200 Favourable
MUV = £2,000 Adverse
Total Material Variance = £200 F + £2,000 A = £1,800 Adverse

Overall, materials cost £1,800 more than standard for the output achieved.

18
Q

What is Labour Rate Variance (LRV)?

A

Measures the effect of paying a DIFFERENT HOURLY RATE to labour than the standard rate. It isolates the impact of wage rate changes from efficiency changes.

19
Q

Labour Rate Variance Formula

A

LRV = (Standard Rate - Actual Rate) × Actual Hours Worked

Where:
- Standard Rate = budgeted hourly wage rate
- Actual Rate = actual hourly wage rate paid
- Actual Hours Worked = total hours actually worked

Favourable if Standard Rate > Actual Rate (paid less per hour)
Adverse if Standard Rate < Actual Rate (paid more per hour)

20
Q

Labour Rate Variance Example 1

A

Standard rate = £12 per hour
Actual rate = £11.50 per hour
Actual hours worked = 2,000 hours

LRV = (£12 - £11.50) × 2,000 = £0.50 × 2,000 = £1,000 Favourable

Paid £0.50 less per hour, saving £1,000 total.

21
Q

Labour Rate Variance Example 2

A

Standard rate = £15 per hour
Actual rate = £16 per hour
Actual hours worked = 1,500 hours

LRV = (£15 - £16) × 1,500 = -£1 × 1,500 = £1,500 Adverse

Paid £1 more per hour, costing £1,500 extra.

22
Q

What causes Labour Rate Variance?

A

Favourable LRV:
- Using lower-grade workers
- Wage rate decreases
- Less overtime
- Efficient rostering

Adverse LRV:
- Using higher-grade workers
- Wage rate increases
- Overtime premiums
- Skilled labour shortage

23
Q

What is Labour Efficiency Variance (LEV)?

A

Measures the effect of labour taking MORE or LESS TIME than the standard hours for the actual output achieved. It isolates the impact of productivity from wage rate changes.

24
Q

Labour Efficiency Variance Formula

A

LEV = (Standard Hours for Actual Output - Actual Hours Worked) × Standard Rate

Where:
- Standard Hours for Actual Output = standard hours per unit × actual units produced
- Actual Hours Worked = actual hours worked
- Standard Rate = budgeted hourly rate

Favourable if Standard Hours > Actual Hours (took less time)
Adverse if Standard Hours < Actual Hours (took more time)

25
Labour Efficiency Variance Example 1
Standard time = 2 hours per unit, Standard rate = £10 per hour Actual production = 500 units Actual hours worked = 950 hours Standard hours for 500 units = 2 hours × 500 = 1,000 hours LEV = (1,000 - 950) × £10 = 50 hours × £10 = £500 Favourable Workers were faster, taking 50 hours less, saving £500.
26
Labour Efficiency Variance Example 2
Standard time = 3 hours per unit, Standard rate = £14 per hour Actual production = 400 units Actual hours worked = 1,300 hours Standard hours for 400 units = 3 hours × 400 = 1,200 hours LEV = (1,200 - 1,300) × £14 = -100 hours × £14 = £1,400 Adverse Workers took 100 hours more than expected, costing £1,400 extra.
27
What causes Labour Efficiency Variance?
Favourable LEV: - Skilled/experienced workers - Good training - Better equipment/tools - Improved processes - Effective supervision - High motivation Adverse LEV: - Inexperienced workers - Poor training - Equipment breakdowns - Material quality issues - Poor supervision - Low motivation
28
Total Labour Variance Formula
Total Labour Variance = Labour Rate Variance + Labour Efficiency Variance Or calculated directly: Total Labour Variance = (Standard Cost - Actual Cost) for actual output
29
Total Labour Variance Example
LRV = £1,500 Adverse LEV = £500 Favourable Total Labour Variance = £1,500 A + £500 F = £1,000 Adverse Overall, labour cost £1,000 more than standard for the output achieved.
30
What is Fixed Overhead Expenditure Variance?
Measures the difference between the budgeted fixed overhead costs and the actual fixed overhead costs incurred. This is a spending variance.
31
Fixed Overhead Expenditure Variance Formula
Fixed Overhead Expenditure Variance = Budgeted Fixed Overheads - Actual Fixed Overheads Favourable if Budgeted > Actual (spent less than budgeted) Adverse if Budgeted < Actual (spent more than budgeted)
32
Fixed Overhead Expenditure Variance Example 1
Budgeted fixed overheads = £50,000 Actual fixed overheads = £48,000 FO Expenditure Variance = £50,000 - £48,000 = £2,000 Favourable Spent £2,000 less than budgeted on fixed overheads.
33
Fixed Overhead Expenditure Variance Example 2
Budgeted fixed overheads = £80,000 Actual fixed overheads = £85,000 FO Expenditure Variance = £80,000 - £85,000 = £5,000 Adverse Spent £5,000 more than budgeted on fixed overheads.
34
What causes Fixed Overhead Expenditure Variance?
Favourable variance: - Rent reductions/negotiations - Lower insurance premiums - Reduced supervision costs - Energy efficiency savings Adverse variance: - Rent increases - Higher insurance costs - Additional supervision - Unexpected repairs
35
What is Fixed Overhead Volume Variance?
Measures the difference between the standard cost of actual production and the budgeted cost. It arises because actual production volume differs from budgeted volume (only in absorption costing).
36
Fixed Overhead Volume Variance Formula
FO Volume Variance = (Actual Units Produced - Budgeted Units) × OAR per unit Where OAR per unit = Budgeted Fixed Overheads / Budgeted Units Favourable if Actual Units > Budgeted Units (produced more) Adverse if Actual Units < Budgeted Units (produced less)
37
Fixed Overhead Volume Variance Example 1
Budgeted production = 10,000 units Budgeted fixed overheads = £120,000 OAR per unit = £120,000 / 10,000 = £12 per unit Actual production = 10,500 units FO Volume Variance = (10,500 - 10,000) × £12 = 500 × £12 = £6,000 Favourable Produced 500 more units, absorbing £6,000 more fixed overhead.
38
Fixed Overhead Volume Variance Example 2
Budgeted production = 5,000 units Budgeted fixed overheads = £75,000 OAR per unit = £75,000 / 5,000 = £15 per unit Actual production = 4,600 units FO Volume Variance = (4,600 - 5,000) × £15 = -400 × £15 = £6,000 Adverse Produced 400 fewer units, under-absorbing £6,000 fixed overhead.
39
What causes Fixed Overhead Volume Variance?
Favourable variance: - Higher demand than expected - Better production efficiency - Fewer breakdowns - Improved capacity utilization Adverse variance: - Lower demand than expected - Production delays - Machine breakdowns - Material shortages - Labour issues
40
Why investigate variances?
1. Identify problems early and take corrective action 2. Learn from favorable variances and replicate success 3. Improve future standards and budgets 4. Assess performance of managers and departments 5. Ensure standards remain realistic and achievable 6. Maintain control over operations
41
When should variances be investigated?
1. When variance is SIGNIFICANT in monetary value 2. When variance exceeds a certain percentage threshold 3. When variance shows a trend (consistently adverse/favourable) 4. When variance is CONTROLLABLE by management 5. When investigation cost is justified by potential benefits
42
What is Management by Exception?
A principle where managers focus attention on significant variances (exceptions) rather than routine items. This saves time and directs effort where it's most needed.