653 - 1 Flashcards

(113 cards)

1
Q

Stage 1: Code permitted Minimum Design Metal Temperature (by material) – This stage involves two
steps: What is Step 1

A

Identify the Material Group for the plate to be used, using Table 4.4b. API 650

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Stage 1: Code permitted Minimum Design Metal Temperature (by material) – This stage involves two
steps: What is Step 2

A

Using Figure 4.1b API 650, determine the Minimum Design Metal Temperature (MDMT) for that
material.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Stage 2: Determining Design Metal Temperature by Location – This stage also has two steps: What is step 1

A

Using Figure 4.2, determine the Lowest One-Day Mean Temperature.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Stage 2: Determining Design Metal Temperature by Location – This stage also has two steps: What is step 2

A

Add 15°F to Lowest One-Day Mean temperature found in step 1 as described in paragraph 3.8.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How can we determine whether a material needs to be impact
tested or not.

A

If the Design Metal Temperature by Location +15 degrees is higher than the Code permitted MDMT (by material) impact testing is not required. If the Design Metal Temperature by Location +15 degrees is at or below the Code permitted MDMT (by material) then impact testing is required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Navigation in API 650 - Name the section/chapter - Material requirements.

A

Section 4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Navigation in API 650 - Name the section/chapter - Design calculations and minimum thicknesses.

A

Section 5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Navigation in API 650 - Name the section/chapter - Rolling and fabrication rules.

A

Section 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Navigation in API 650 - Name the section/chapter - Onsite construction requirements

A

Section 7

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Navigation in API 650 - Name the section/chapter - NDE rules

A

Section 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Navigation in API 650 - Name the section/chapter - Bottom foundation requirements

A

Annex B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The required thickness of a tank shell shall be the greater of:

A
  • the calculated design thickness using product stress formula
  • the calculated hydrostatic stress thickness
  • the minimum required thickness from paragraph 5.6.1.1
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the below formula used to determine.

       2.6D(H-1)G Td = \_\_\_\_\_\_\_\_\_\_\_\_\_ + CA
               Sd
A

Design Shell Thickness Formula

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the below formula used to determine.

       2.6D(H-1) Tt = \_\_\_\_\_\_\_\_\_\_\_\_\_ 
               St
A

hydrostatic test shell thickness

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the below formula used to determine.

           2.6D(H-1)DG Tmin = \_\_\_\_\_\_\_\_\_\_\_\_\_ 
               SE
A

For determining the minimum thickness of an entire shell course

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the below formula used to determine.

           2.6HDG Tmin = \_\_\_\_\_\_\_\_\_\_\_\_\_ 
               SE
A

For determining the minimum acceptable thickness of a locally thinned area

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is nomenclature for the formula used to determine.

           RT- MRT Or = \_\_\_\_\_\_\_\_\_\_\_\_\_ 
           StPr+UPr
A

RT = remaining thickness
MRT = minimum remaining thickness (taken from Table 4.4)
StPr = topside corrosion rate
UPr = underside corrosion rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

In a product fill height calculation, the stress will be on the material for the rest of the interval until
the next scheduled inspection, so the value of tmin to use in the formula is:

A

tmin in product fill height calculation = tmin – (Interval x Corrosion rate)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

In a hydrostatic test height, the stress on the material is only for one day, so the value of tmin to use in the formula is:

A

The current
value of tmin or actual thickness

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

When calculating the value to be used for “H” in a product fill height or hydrotest formula, what do the formulas only solve for.

A

Formulas only solve for the height of water or product above the area
of interest.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

On API 571 what is the way to solve pretty much every damage mechanism.

A

Through Design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What should you consider if you
get asked a question about how to mitigate or prevent a damage mechanism.

A

Design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

When we consider corrosion damage to materials, what is the worst to best in regards to corrosion resistance.

A

a. Carbon steel is the worst material for corrosion resistance
b. Austenitic stainless steel (300 series SS) is better
c. Duplex stainless is very good
d. Nickel is the best material for corrosion resistance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

The most likely critical factors for all
corrosion mechanisms include

A

a. Temperature - everything gets worse when it gets hotter
b. Velocity - everything is damaged more when the velocity is higher
c. Oxygen concentration - almost all corrosion becomes worse when the oxygen
content is increased

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
The most likely critical factors for acid corrosion mechanisms include
a. Acid concentration b. Temperature c. Velocity
26
Identify what NDE to use - Fatigue, all types of stress corrosion cracking, CUI, corrosion and erosion- that are present with surface breaking indications
Use MT or PT as your first choice depending on the material
27
Identify what NDE to use - HIC, SOHIC
Use volumetric NDE to see "inside" the material to where the hydrogen bubbles are forming and cracking
28
Identify what NDE to use -Metallurgical changes - graphitization, carburization
Metallographic replication and lab analysis to identify
29
What are the following paragraphs pertaining to in ASME Section IX - QW-200
WPS & PQR Development
30
What are the following paragraphs pertaining to in ASME Section IX - QW-300
Performance Qualification
31
What are the following paragraphs pertaining to in ASME Section IX - QW-152, QW-153
Tension test procedure and acceptance criteria.
32
What are the following paragraphs pertaining to in ASME Section IX - QW-162, QW-163
Bend test procedure and acceptance criteria.
33
What are the following paragraphs pertaining to in ASME Section IX - QW-253
SMAW procedure development variables.
34
The WPS requires what variables on the WPS
All essential and non-essential variables on the WPS
35
The PQR requires what variables on the WPS
essential variables only are required on the PQR.
36
What is the following table pertaining to in ASME Section IX - Table QW-416
Comparison between welding processes of the essential performance qualification variables.
36
What are the following paragraphs pertaining to in ASME Section IX - QW-353
SMAW performance qualification variables.
37
What is the following table pertaining to in ASME Section IX - Table QW-451.1
Procedure qualification limits and type and number of tests required.
38
What is footnote 1. pertaining to in ASME Section IX - Table QW-451.1
Three variables in footnote 1 – ½”pass rule, less than ½” GMAW-S rule for both base metal and weld metal
39
What is the following tables pertaining to in ASME Section IX - Tables QW-452.1(a), (b), Table QW-452.3, Table QW-461.9
Performance qualification only. Four tables to determine number of tests, thickness qualified, size qualified and positions qualified.
40
Tank Grades – The grade or surface that a tank will rest on SHOULD be constructed at
SHOULD be 1 foot above surrounding grade
41
Tank Grades – The grade or surface that a tank will rest on SHALL be constructed at
SHALL be a minimum of 6 inches after settlement.
42
What is the recommended final layer under the tank bottom
Clean washed sand 3 to 4 inches deep.
43
Tank shall be crowned (sloped) at a ration of
1:120 inches (1 inch in 10 feet)
44
Concrete ringwalls shall be how thick?
Not less than 12 inches thick
45
Concrete ring walls shall be located at least where?
2 feet below the lowest adjacent finished grade.
46
Bottom plates shall have a corroded thickness of not less than
.236"
47
How many inches of the bottom plate shall project past the shell
At least 2 Inches or the projection shall allow ½ inch from the toe of the shell-to-bottom fillet to the edge of the projection – whichever is greater.
48
Three plate laps in the bottom plates of a tank shall be at what distance to each other
at least 12 inches from each other, the tank shell, and from joints between the annular plates and the bottom.
49
Required thickness of a tank shell SHALL be what?
The greater of the design shell thickness – INCLUDING corrosion allowance – or the hydrostatic test shell thickness, but not less than what is shown in 5.6.1.1
50
Vertical shell joints shall be offset by?
At least 5t where t is the thickness of the thicker plate at the point of offset
51
Shell-to-bottom fillet weld sizes
Not more than ½ inch, and not less than the nominal thickness of the thinner of either the shell plate or the bottom plate, but not less than the minimums in the table in API 650 5.1.5.7 a)
52
Roof plate thickness shall not be less than
3/16 inch (or 7-gauge sheet) plus any applicable corrosion allowance.
53
Maximum top angle weld on a frangible roof is
3/16 inch welded on the top side only.
54
Floating roof deck plates shall have a minimum nominal thickness of
3/16 inch.
55
Sleeves and fittings used on floating roof decks shall have a minimum wall thickness of
¼ inch for all pipe and plate construction
56
Floating roofs shall be able to withstand a
10-inch rainfall in a 24-hour period with the primary drains inoperative.
57
Primary roof drains shall be not smaller than NPS 3 if the tank is
If the tank is less than 120 feet in diameter, and not smaller than NPS 4 for roofs with a diameter greater than 120 feet.
58
Roof support legs shall have at least two settings –
High roof clearance of 78 inches and a minimum clearance for tank internals of 3 inches.
59
Floating roof penetrations shall have a seal that will permit what?
A local deviation in travel of ±5 inches.
60
Minimum size of fillet welds shall be as follows - Plates 3/16 inch thick the weld shall ?
Full thickness fillet weld
61
Minimum size of fillet welds shall be as follows - Plates more than 3/16 inch thick the weld thickness shall -
Not be less than one-third the thickness of the thinner plate and shall be at least 3/16 in.
62
Routine in-service inspection is completed at what intervals
At intervals consistent with the conditions on-site but shall not exceed 1 month
63
Routine in-service inspections can be completed by who?
Can be done by owner/operator personnel
64
Visual external inspection shall be completed at what interval?
Every 5 years or RCA/4N – whichever is less.
65
UT thickness inspection where the corrosion rate is not known shall be competed when?
Every 5 years if the owner/operator has decided to use this method.
66
UT thickness inspection where the corrosion rate is known shall be completed when?
The the smaller of RCA/2N or 15 years.
67
Internal inspection of the shell is an acceptable substitution for external UT thickness inspection if the?
Internal inspection interval is equal to or less than the UT interval.
68
What is the Internal initial inspection interval
10 years + any safeguards but not more than 20 years if there is no RPB, or no more than 30 years if there is an RPB
69
What are the types of bottom settlement.
uniform settlement rigid body tilting out-of-plane
70
Which type of bottom settlement may impede the proper functioning of the floating roof
Out-of-plane settlement
71
When shall Roof plates be replaced.
When its corroded to less than 0.09 inches in any 100 in.², or any roof plates with holes shall be replaced
72
Evaluation of the existing tank shell is carried out by who?
An engineer.
73
Critical length “L” shall not be more than?
40 inches in any situation
74
The minimum acceptable thickness in any tank shell course shall not be less than
0.1 inch
75
Criteria for continued operation of a tank shell always includes adding what?
The corrosion allowance to the calculated thickness
76
Joint efficiency for a welded tank is 1.0 provided the area being considered is what?
More than 1 inch or 2 times the plate thickness.
77
Joint efficiency for a riveted tank is what
1.0 only when away from the rivets by at least 6 inches
78
Minimum Remaining Thickness (MRT) at the next inspection for the bottom plate is a minimum of what?
Minimum of 0.10 inches with no lining or means of detection of a leak.
79
The interval for tank bottom inspection (Or) is calculated using a simple Remaining Life formula which is -
RT (what do you have today) – MRT (minimum value from Table 4.4) divided by the total corrosion rate (add bottom corrosion rate to the topside corrosion rate) RT – MRT / CR = Or
80
Minimum dimension for a replacement plate is
2 inches or 12 times the thickness of the replacement plate – whichever is greater.
81
What should you do prior to welding new vertical joints in repair plates.
Cut existing horizontal welds for a minimum of 12 inches beyond the new vertical joints, and weld the new horizontal joints last.
82
Maximum size of hot tap nozzles in a tank with unknown toughness is what?
NPS 4
83
Hot tap nozzles shall be made of
Schedule Extra Strong Pipe
84
There shall be a minimum of how many feet of liquid above the hot tap location.
3 feet of liquid above the hot tap location.
85
Materials affected by soil corrosion include
Carbon steel, cast iron and ductile iron
86
Acceptance criteria for radiographs of repair welds on an in service tank
API 650
87
When examining duplex stainless steel materials using the PT method
All penetrant materials shall be analyzed individually for chlorine and fluorine content
88
There shall be a minimum of 3 feet of liquid above the hot tap location.
<_ 1/2"
89
Coating bond failures commonly occur where?
Below seam leaks
90
Minimum thickness of any shell course being evaluated for suitability for service shall not be less than
.100"
91
The Maximum weld pass thickness for reconstructed tanks on horizontal and vertical welds in tank shell courses that have material over 1.5" thick shall be
.75"
92
Preheat zone shall have the temperature raised to the correct preheat temperature within
3" of the place the welding will be started
93
The concept of endurance limit is primarily applied to -
Smooth Bars (Eg. Pump Shaft)
94
Use of oxyfuel welding process is not permitted
for tanks that require impact testing
95
Internal floating roofs shall be repaired in accordance with what Annex if the original drawings are not available.
API 650 Annex H
96
A lamination can be repaired in plate that shall be used to fabricate a tank provided that it does not exceed
3" Long and 1" in depth
97
ASME Section IX restricts the use of volumetric NDE for procedure qualifications to which welding process
ALL - Volumetric NDE is not permitted for procedure qualification
98
How far away from Rivets and seams must an area to be in order to considered as having a joint efficiency of 1.0
6"
99
What are Acceptable codes that welding procedures for the repair and alteration of tank stairways, handrails and other miscellaneous assemblies
AWS D1.1 ASME Section IX AWS D1.6
100
Steel in an internal floating roof that is in contact with vapor or liquid shall be a minimum nominal thickness of
3/16"
101
Maximum undercut allowable by visual examination on vertical butt joint
1/64"
102
Change of service to operation at elevated temperatures
API650 Annex M
103
The arc stuf welding process is limited the attachment of studs that are
3/8" Diameter
104
To ensure the adhesion neccessary for long term performance of a tank liner, the anchor pattern must be
Sharp and Angular
105
Penetrations larger than NPS4 shall be installed with the use of an insert plate if the shell plate thickness is
>1/2"
106
Each radiograph shall clearly show a minimum of
6" of weld length
107
Qualification of stud welding procedures shall involve welding and testing of
10 Studs
108
Concentration cell corrosion may cause pitting of a bare steel tank bottom at a rate as high as
80 Mils/per year
109
The minimum size of the letters on a replacement or reconstructed nameplate shall be
5/32"
110
What is the minimum thickness allowed by api 653 for a new roof rim
3/16"
111
What is the likely location of oxygen cell corrosion
under a surface deposit
112