who pays for the building permit?
contractor
what are examples for when a warranty doesn’t apply?
damage from abuse, alterations not in contract, improper maintenance, normal wear and tear
who buys the materials?
contractor
how long until owner has the right to carry out the work?
10 days
how long does contractor have to give notice of unknown/concealed conditions?
21 days
how long does architect and owner have to review the superintendant?
14 days
When is the architect’s duty to administer the contract complete?
It terminated when architect issues the final certificate for payment
The Initial Decision Maker will review claims between the Owner and Contractor within ____ days.
10