What are some of the tools and techniques you can use to perform qualitative risk analysis?
Interpersonal and team skills
Risk probability and impact assessment
Risk categorization
Expert judgment
Probability and impact matrix
Meetings
Interviews
Expert judgment
- This is a correct option. You may need specialized expertise and advice in order to perform qualitative risk analysis effectively.
Interpersonal and team skills
- This is a correct option. In order to effectively manage interviews and team meetings, you’ll need to have strong interpersonal skills, such as facilitation skills, to keep participants engaged in the tasks at hand and to resolve conflicts.
Assessment of risk parameters
- This is a correct option. Assessing risk parameters is a data analysis technique that enables you to gain different perspectives on identified risks.
Hierarchical charts
- This is a correct option. Hierarchical charts are one method of data representation that allow you to categorize more than two parameters at a time when performing a qualitative risk analysis.
Risk categorization
- This is a correct option. Risk categorization helps you analyze risks by grouping them together according to their sources.
Meetings
- This is a correct option. When carrying out a qualitative risk analysis, you may need to organize workshops with the project team to discuss, classify, and rate risks.
Data gathering
- This is a correct option. Data gathering – specifically interviewing – is an important way of discovering individual risks that could affect your project.
you calculate priority scores for your project’s risks:
funding shortages: 0.06
staffing shortages: 0.05
loss of key personnel: 0.2
resource problems: 0.28
Rank risk priorities from highest to lowest.
Resource problems
- A risk priority rating of 0.28 ranks the resource problems risk as the highest priority risk in this case.
Loss of key personnel
This should be number 2 in the sequence. - A risk priority rating of 0.2 ranks the loss of key personnel risk as the second highest priority risk.
Funding shortages
This should be number 3 in the sequence. - A risk priority rating of 0.06 ranks the funding shortages risk as the third highest priority risk.
Staffing shortages
- A risk priority rating of 0.05 ranks the staffing shortages risk as the fourth and lowest priority risk.
Project document updates are the typical outputs of a qualitative risk analysis.
Which documents are updated?
What are the common inputs to the Perform Quantitative Risk Analysis process?
Risk-related information from previous projects
Risk databases
Basis of estimates
Schedule baseline
Scope baseline
- This is a correct option. The scope baseline is a part of the project management plan that outlines activity durations, which may be affected by potential risks.
Risk register
- This is a correct option. An important project document, the risk register details project risks you need to analyze and assign numeric values to during quantitative risk analysis.
Historical information
- This is a correct option. Historical information is an organizational process asset that enables you to discover what unplanned events and strategies were used in previous projects that may apply to your current one.
Industry studies of similar projects
- This is a correct option. Enterprise environmental factors, like industry studies and risk databases, provide valuable insight when carrying out a quantitative risk analysis.
You’re assessing the possible costs of completing an upgrade to your organization’s network.
What are some of the examples of information you should obtain during a risk data gathering interview?
What are the different types of continuous distribution?
What is the purpose of sensitivity analysis?
To determine which risks have the greatest potential impact
- This is the correct option. Sensitivity analysis involves identifying the relative potential impacts of different risks on project objectives. Based on the results, you can rank risks from greatest to least likely impact.
You determine that if new machinery is ordered, there’s a 40% probability it will take 14 days to arrive and a 60% probability it will take 28 days.
What is the total EMV for ordering the machinery?
22.4 days
To calculate the EMV for a risk, you multiply its potential impact by its probability. In this case, you multiply 40% by 14 days and 60% by 28 days and add the totals together.
The results of a cost risk simulation display on a cumulative chart.
Which statement describes what the highlighted point is communicating about the cost-related risk?
There is a 25% chance that the project will meet a budget requirement of $43 million
- This is the correct option. The probability reading at the $43 million mark is 25%, indicating that the project has a 25% chance of costing $43 million.
What information is generally updated in the risk report once the Perform Quantitative Risk Analysis process is completed?
Which examples are inputs to the Perform Qualitative Risk Analysis process?
Risk management plan
Risk register
Enterprise environmental factors
Organizational process assets
You calculate priority scores for project risks:
calculation errors: 0.14
substandard materials: 0.24
toxic waste spill: 0.2
inadequate safety procedures: 0.08
Rank risk priorities from highest to lowest.
Substandard materials
Toxic waste spill
Calculation errors
Inadequate safety procedures
What are some of the examples of information you should obtain during a risk data gathering interview?
Risks that could impact project costs include staff shortages and the need to rework problems that arise during quality testing
Selected
Incorrect answer.
Given a worst-case scenario, the total cost of the project could go as high as $6.5 million
Not selected
Correct answer.
The most likely total cost of the project will be in the region of $4.8 million
Selected
Correct answer.
The probability estimates are based on costs of a previous similar project, which faced comparable risks
Selected
Correct answer.
Optimistically, the lowest total cost of the project will be $2.5 million
Selected
Correct answer.
What types of information should you update in a risk report as a result of the Perform Quantitative Risk Analysis process?
What elements should you update in a risk report as a result of the Perform Quantitative Risk Analysis process?
Prioritized list of individual project risks
Recommended risk responses Not selected Correct answer. Assessment of overall project risk exposure Selected Correct answer. Detailed probabilistic analysis of the project Selected Correct answer. Trends in quantitative risk analysis results Selected Correct answer.