Where does the risk lie with an approximate bill?
Quantity - the Client
Price - the Contractor
Why was an approximate bill used over a CSA?
What is the benefit of a measurable contract?
How are valuations undertaken
Do changes to approximate quantities need to be instructed?
only if the sum allowed for within the bill is not reasonably accurate, or if the architect wishes to instruct drawings that have defined quantities
When are quantities remeasured under an approximate bill
during valuations the actual amount of work done must be valued.