A.I.R
3 F
R
Artist In Residence
Third Floor
Rear
Sign specifications established by DoB for Artists Residential Occupancy shall be:
Metal 8”x10”
2” Black letters on a White Background
7 feet Above sidewalk level
As Close As Possible to the MAIN ENTRANCE on the front wall outside of building
NEW BUILDING
When the working deck reaches a height of _____ or greater above the ground in a building for which a standpipe is required:
75 feet
a Permanent or Temporary standpipe system shall be kept in a state of readiness at all times for use by fire-fighting personnel.
No standpipe shall be considere to be in a state of readiness unless it is:
PAINTED RED
Construction on New Building:
The standpipe system shall serve all floors:
Where the PERMANENT STAIRS are required
Where is the standpipe riser capped in a building under going demo?
Capped Above the Outlet ON THE FLOOR IMMEDIATELY BELOW the floor being demolished.
Ex. Demo 30 - capped above 29th floor outlet
Standpipe Pressurized Alarm Systems:
New Buildings higher than 75 feet-
Temporary and Permanent dry standpipes must have an air-pressurized alarm
Prior Notification for scheduled work: contractors must
notify Fire Department before any planned alarm deactivation
Fire Dept hose connections shall be kept free from obstruction and shall be marked by a metal sign reading “Standpipe Connection” and:
by a RED LIGHT at Night
Standpipes may be used for a purpose other than to supply water for firefighting operations, like supplying water or compressed air for construction or demo ops:
provided At Least ONE standpipe riser is maintained at all times for firefighting ops
All Exposed standpipes and sprinkler piping must be painted:
RED
exception - Branch piping
Dedicated standpipe valve handles must be painted:
RED
Combination standpipe valve handles must be painted:
YELLOW
Dedicated sprinkler valve handles must be painted:
GREEN
A metal sign must be present at the siamese connection for the sprinkler system reading “SPRINKLER SIAMESE CONNECTION” with;
a RED LIGHT over the sign; MUST BE LIT AT NIGHT
Sprinkler System Requirements:
The red paint shall be maintained during:
ANY alteration operation
When demolition starts, the sprinkler risers shall be capped:
immediately below the floor being demolished
During the course of construction of a new building, or in spaces being added to an existing building, at least one permanent stair shall be brought to within:
a distance of 40 feet OR 4 Floors below the Working Deck at all times
In all other locations where permanent stairs will be required, a temporary or permanent stair shall be brought:
to within a distance of 40 feet or 4 floors below the working deck at all times
Whenever construction or demolition work reaches a height greater than ______ at least one elevator kept in readiness at all times for fire department use.
75 feet
The maximum distance between the highest accessible floor from a temporary elevator or hoist and the working deck of the building under construction or demolition:
shall be no more than 75 feet OR 7 floors
What is the working deck in
2. floor where metal decking and steel components are being placed BEFORE CONCRETE IS POURED
Open fires shall be constantly attended until the fire is extinguished. A minimum of:
one portable fire extinguisher or garden hose connected to an Approved water supply, shall be available for immediate use.
If devices similar to Open Fires (like patio fireplace, solid-fuel burning portable heaters etc) are found by Fire officials, they should:
Order the use of these devices DISCONTINUED IMMEDIATELY
No further action required at this time