At concrete form inspection, the inspector checks for what?
Bearing surface
No standing water
Rebar installed correctly
What is required prior to a framing inspection
Electrical, plumbing, heating and ventilation rough ins
What must be done to the outside of a building prior to installing insulation
Must be weather tight
When is perimeter drainage inspected
Prior to backfill
Which inspections require a pressure test
Water and waste
Gas
Sprinkler system
What is inspected at the rough on stage of electrical construction
Main service and all wiring
What is the man concern at the final inspection
Handrails Guards Building address number Smoke Heat Co2 Alarms Other safety requirements