Government legislation to ensure fire safety of new builds and refurbishment projects.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
What is a HRB?
A
2 Resi units
18m high
7 storeys
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
What is the Gateway process?
A
Gateway 1 - planning permission. Demonstrate that fire risk has been considered in the design.
Gateway 2 (12-week) - submission of prescribed documents for approval before construction can commence.
Gateway 3 (8-weeks) - submission of completion information and as builts inline with prescribed documents. Approval required before occupation.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
What are prescribed documents?
A
Competency declaration
Building regulations compliance statement
emergency file
construction plan
A change control plan
A mandatory occurrence reporting plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
How is change treated?
A
Notifiable changes must be notified to the BS before the works can be carried out.
“Major changes” a change control application must be made and approved before the works can be undertaken. The BBS then has six weeks to make its decision.