What was the health and safety incident?
How did you ensure health and safety of the site?
A structural report was commissioned before your involvement. Why did you visit with another structural engineer?
What considerations did you undertake in respect of the local listing?
How can you tell the building is constructed of solid walls?
What is clinker? How did you establish it was clinker?
What procurement route did you use and why?
Why did you choose a minor works contract?
What cause the significant cost increase from Contract Sum to final account?
How did you select the contractors?
How did you provide regular updates?
What was included in your site inspection reports?
Why were the works notifiable?
Why did you choose to appoint an approved inspector?
What pre-construction risks did your designers identify?
What residual risks did you identify?
What defects did you identify? How?
Can you describe delamination of steel joists? How did you establish this?
Why was a timber frame used over steel or traditional construction?
How did you select the joists and centres for Roof 1?
What is the difference between C16 and C24?
How were the joists supported?
How did the contractor carry out the joist & deck installation?
What was the roof build-up?