Have you been granted consent to use names of Client and project?
Yes, email from Oliver Buckingham of Pitalia
What is a Grade II* listed building?
Particular important buildings of more than special interest, 5.8% of listed buildings are II*
How did you include Amendments to the JCT D&B?
The Client’s lawyer drafted these, excluded Coronavirus as a Relevant Matter, Employer could deduct £5k per document not included in the O&M’s
Why were the consultants not novated?
Why was a Minor Works contract necessary?
To de-risk the main project and get rid of any unknowns for the main works, increases interest for tenderers
How did you establish the Client’s objectives?
Had a meeting with them at the start to define their objectives and red lines, to ensure I was able to fulfil the role/ scope of services sufficiently
Why did you not select Standard Building Contract if quality key driver?
What involvement did you have with tenants?
None, this was driven through the Client
What RIBA stage was it when the project went out to tender?
Stage 4
What stage was the previous cost plan on?
Stage 3
What assumptions were made in the Cost Plan?
What increased from the original Cost Plan?
How did you deal with tenderers dropping out?
What is Value Engineering?
Deriving a good quality product with a cost effective solution
Difference between VE and cost cutting?
How did you de-risk the project with there being a lot of Provisional Sums?
Ensured I monitored them in the Cost Report and instructed them when appropriate
What is force majeure?
Unforeseen event that prevents fulfilment of the contract, beyond control of both parties such as war
Did the Contractor apply for Loss and Expense?
No
What is required to claim for Exceptionally Adverse Weather?
Did the contract not become at large if no EoT was issued?
How was the arrangement ratified in the Final Account?
Stated it was full and final settlement including any claims
What were the Provisional Sums in the Contract?
Why was a JCT D&B selected?
What are roles of QS pre and post contract?
Pre - Cost plan, tender process, contract documents
Post - Valuations, variations, final account