Why did you use NC3 Vs NEC 4
Because it was requested by the client due them being familiar with it
What is the difference between NEC3 and NEC4
what was included in your feasibility?
What did you advise the client for the limitations
Are you competent to be designer and principle designer ?
Yes i am for CDM but not for BSA
How would you determine if an area needs to be compartment.
I would check the fire a risk assessment, i would aso advise the client that if this was not up to date that it is required to be updated.
Are you competent to do a fire risk assessment ?
yes - has to be a responsible person, usually someone who is responsbile for the building and
How would you determine if building requires an R&D survey.
If the Building was built pre 2000 - and there was no record of R&D survey having already been undertaken - would you require one if their was an asbestos management plan
who would you use to carry out asbestos work?
Licensed vs non licensed and notifiable
What is the difference between Licensed vs non licensed and notifiable
When a variation occurs how do you tackle it ?
So the contractor may raise a early warning or CE - if it requires a site visit i would undertake one to check what the contractor was claiming was correct. Contractor instructed to submit a quote - 3 weeks - contractor question - 2 weeks - the PM responds
What legislation is associated with asbestos
The uses of asbestos was banned in 1999. The control of asbestos 2012
What is relevant event JCT ?
An event that causes a delay to the completion date which is caused by the client or a neutral event.
Variations.
Exceptionally adverse weather.
Civil commotion or terrorism.
Failure to provide information.
Delay on the part of a nominated sub-contractor.
Statutory undertaker’s work.
Delay in giving the contractor possession of the site.
Force majeure (such as a war or an epidemic).
Loss from a specified peril such as flood.
The supply of materials and goods by the client.
National strikes.
Changes in statutory requirements.
Delays in receiving permissions that the contractor has taken reasonable steps to avoid.
How would you determine adverse weather ?
Where weather over a calendar month has occurred on average less frequently than once in ten years - JCT does not define it
What is a relevant matter JCT?
A matter which the client is responsible for that materially effects the progress of the works - can claim for direct loss and expense.
Failure to give the contractor possession of the site.
Failure to give the contractor access to and from the site.
Delays in receiving instructions.
Opening up works or testing works that then prove to have been carried out in accordance with the contract.
Discrepancies in the contract documents.
Disruption caused by works being carried out by the client.
Failure by the client to supply goods or materials.
Instructions relating to variations and expenditure of provisional sums.
Inaccurate forecasting of works described by approximate quantities.
Issues relating to CDM.
Why does NEC use CE instead ?
They do not treat compensation events as an allocation of blame, but rather an allocation of risk. Any risk that is not specifically identified as being attributed to the client is borne by the contractor.
What is a requirement to go into contract ?
1) Offer
2) Acceptance
3) Consideration
4) Intent to make legal relations
What clause would you refer to for cooperation in NEC ?
Clause 10.2 - he Parties [which means the Contractor and the Client], the Project Manager and the Supervisor act in a spirit of mutual trust and co-operation
What is the difference between partial possession and sectional completion ?
Sectional Completion = different completion dates for different sections of the works allowing the client to take partial possession of the completed parts whilst construction continues - Multiple completion dates - each section must be clearly defined and the amount of retention released for that section must specified for each section. Follows the usual handover procedures. Some work in the section may remain outstanding such as completion of commissioning as built ect which will cross over sections
Partial Possession = the same as sectional but after the contract documents are drawn. The contractor is not obliged to allow partial possession (although PP cannot be unreasonably withheld) and may not wish to e.g. access routes are difficult to achieve, disrupt the works, incur additional costs - occupants may disrupt the works which could result in a claim for an extension of time and/or loss and expense
What is your role in stage 7 ?
What are the limitations of NBS ?
Early warning vs Risk Reduction Meeting ?
NEC4 vs NEC 3
What NEC Clause is for compensation events?
60.1
How Frequently should scaffolding be checked