Why was Design & Build the most appropriate procurement route for this project?
The Design & Build approach allowed the employer to set out required outcomes while the contractor developed the detailed design.
What were your key responsibilities as Employer’s Agent under JCT D&B 2016?
My role started at RIBA Stage 3 and continued through Stages 3 to 6.
How did your role differ from that of a Contract Administrator?
Unlike a traditional contract, my role involved managing the contract rather than administering a fully employer-designed scheme.
What were the key risks associated with delivering works in a live school environment?
Safeguarding was paramount throughout the project.
Why was the original CIF-approved design considered unsuitable?
A post-funding feasibility review highlighted these issues.
What were the risks of changing the design after CIF approval?
Formal scope change request to the DfE was required for any changes.
How did you manage the DfE approval process for the scope change?
The scope change was approved after ensuring it remained deliverable within existing CIF allocation.
Why did you not proceed with a full redesign and re-tender?
A controlled redesign within the existing procurement route was considered more appropriate.
How did you ensure the revised design remained within budget?
Ensured the revised scheme could be delivered within the approved CIF allocation by using contingency.
What would you have done if the revised design exceeded the CIF funding?
Proceeding without funding certainty on a CIF-funded project would not be advised.
How did you validate the contractor’s pricing for the revised design?
This validation was crucial to maintain financial control.
What cost control mechanisms did you implement during the project?
Protected the client from unnecessary costs by rejecting a variation that fell within contractor’s design responsibility.
On what contractual basis did you reject the contractor’s variation claim?
The ramp and retaining wall were considered part of the contractor’s design responsibility.
How did you determine that the contractor held the risk for the level issue?
Concluded contractor should have accounted for site levels in their proposals.
What evidence did you rely on to support your position?
These documents demonstrated that compliant access was part of the contractor’s obligations.
What would you have done if the contractor disputed your decision?
If disagreement continued, I would advise the client on dispute resolution options under the contract.
How is risk allocated under a JCT Design & Build contract?
Important for assessing whether issues are variations or contractor responsibilities.
Can you give examples of Employer’s Risks vs Contractor’s Risks on this project?
Under D&B, contractors are responsible for their design development unless excluded.
How did you ensure the project was delivered within the 7-month programme?
Addressed issues promptly to avoid unnecessary delays.
What would you have done if the project started to fall behind programme?
Consideration of CIF deadlines, school operations, and costs would be essential.