What is the name of the case study?
CBRE Limited, 1st Floor, 3 Chamberlain Square – CAT B Office Fit-Out
What are the dates for the project?
January 2024 – December 2025
What is the confidentiality statement regarding this case study?
The information is confidential and for the Assessment of Professional Competence. It is not to be used by anyone other than those authorized by the Royal Institution of Chartered Surveyors.
What does the acronym BREEAM stand for?
Building Research Establishment Environment Assessment Methodology
What is the main purpose of the CAT B fit-out for CBRE Limited?
To create a working environment that meets the Client’s requirements within a budget of £2.3m.
What were the key requirements for the Client in this project?
What role did I perform in the project?
Project Manager (PM) and Employers Agent (EA)
What was the primary approach for tendering in this project?
The Client chose to procure the project through the Design and Build route.
What were the three tendering options explored?
What was the limitation of the Single Stage Competitive Tender option?
It lengthened the overall programme, preventing Practical Completion before the lease expiry date.
What was the advantage of the Two Stage Competitive Tendering approach?
It allowed early Contractor involvement which reduces construction risk and ensures accurate pricing.
What was the proposed solution for tendering?
Negotiated Tender with OP as the preferred Contractor.
What significant change was introduced during RIBA Stage 2?
The project needed to achieve BREEAM Excellent.
What caused the RIBA Stage 2 cost estimate to be over budget?
Additional professional fees, design changes, and construction costs related to achieving BREEAM Excellent.
What were the options reviewed to manage the over budget issue?
What was the recommended solution to address the cost over budget?
Conduct a Value Engineering Exercise.
What was the key issue regarding the tendering process?
The need for timely completion to meet the Client’s lease expiry date.
What does the acronym ESG stand for?
Environmental Social Governance
Fill in the blank: The initial cost estimate over budget was by _______.
£164k
True or False: The Client agreed to reduce the target accreditation level for BREEAM.
False
What was a key consideration during the procurement process?
Demonstrating fairness, transparency, and value for money.
What is the role of the QS team in the project?
Conduct thorough reviews of the Contract Sum Analysis to ensure value for money.
What was the main goal of the value engineering (VE) workshop?
To analyze optional items and maximize BREEAM credits while minimizing costs.
What did the analysis of alternative materials and procurement methods aim to achieve?
Maximize value for money and offset additional sustainability costs.