Case Study (AI) Flashcards

(45 cards)

1
Q

What is the name of the case study?

A

CBRE Limited, 1st Floor, 3 Chamberlain Square – CAT B Office Fit-Out

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the dates for the project?

A

January 2024 – December 2025

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the confidentiality statement regarding this case study?

A

The information is confidential and for the Assessment of Professional Competence. It is not to be used by anyone other than those authorized by the Royal Institution of Chartered Surveyors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does the acronym BREEAM stand for?

A

Building Research Establishment Environment Assessment Methodology

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the main purpose of the CAT B fit-out for CBRE Limited?

A

To create a working environment that meets the Client’s requirements within a budget of £2.3m.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What were the key requirements for the Client in this project?

A
  • CAT B fit-out of 1st Floor within set budget of £2.3m
  • Practical Completion ahead of lease expiry
  • Multiple working zones
  • Provision for future occupancy expansion
  • BREEAM accreditation
  • Single point of responsibility for design and construction
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What role did I perform in the project?

A

Project Manager (PM) and Employers Agent (EA)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What was the primary approach for tendering in this project?

A

The Client chose to procure the project through the Design and Build route.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What were the three tendering options explored?

A
  • Single Stage Competitive Tender (JCT D&B)
  • Two Stage Competitive Tender (JCT D&B)
  • Negotiated Tender (JCT D&B)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What was the limitation of the Single Stage Competitive Tender option?

A

It lengthened the overall programme, preventing Practical Completion before the lease expiry date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What was the advantage of the Two Stage Competitive Tendering approach?

A

It allowed early Contractor involvement which reduces construction risk and ensures accurate pricing.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What was the proposed solution for tendering?

A

Negotiated Tender with OP as the preferred Contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What significant change was introduced during RIBA Stage 2?

A

The project needed to achieve BREEAM Excellent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What caused the RIBA Stage 2 cost estimate to be over budget?

A

Additional professional fees, design changes, and construction costs related to achieving BREEAM Excellent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What were the options reviewed to manage the over budget issue?

A
  • Scope Reduction
  • Request Additional Project Funding
  • Conduct Value Engineering (VE) Exercise
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What was the recommended solution to address the cost over budget?

A

Conduct a Value Engineering Exercise.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What was the key issue regarding the tendering process?

A

The need for timely completion to meet the Client’s lease expiry date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What does the acronym ESG stand for?

A

Environmental Social Governance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Fill in the blank: The initial cost estimate over budget was by _______.

20
Q

True or False: The Client agreed to reduce the target accreditation level for BREEAM.

21
Q

What was a key consideration during the procurement process?

A

Demonstrating fairness, transparency, and value for money.

22
Q

What is the role of the QS team in the project?

A

Conduct thorough reviews of the Contract Sum Analysis to ensure value for money.

23
Q

What was the main goal of the value engineering (VE) workshop?

A

To analyze optional items and maximize BREEAM credits while minimizing costs.

24
Q

What did the analysis of alternative materials and procurement methods aim to achieve?

A

Maximize value for money and offset additional sustainability costs.

25
Why was it important to gain the Client's feedback during the secondary meeting?
To agree on which items could be omitted, targeted for further consideration, or remain included.
26
What elements in the cost plan were identified by the Client to reduce the Contract sum?
Operational expenditure items such as planting and coffee machines.
27
What was the outcome of the approach taken in the project regarding BREEAM?
The Client achieved BREEAM Excellent without negatively affecting functional and aesthetic features.
28
What was the significance of conducting a VE exercise?
It contributed to sustainability goals by optimizing designs to minimize resource use, reduce waste, and lower costs.
29
What did the author learn about providing project-specific advice?
The importance of clear, reasoned advice while recognizing programme as a critical driver in the time, cost, quality balance.
30
What was the initial cost estimate situation noted in the document?
The Stage 2 cost estimate was confirmed as over budget.
31
What approach was taken when the cost estimate was over budget?
Created a VE schedule and arranged a VE workshop with key project stakeholders.
32
What did the author emphasize in their approach to managing costs?
Transparency and collaboration across all parties.
33
What was the Client's response to the solutions presented after the VE exercise?
They agreed to proceed with the option that realigned the project with the budget.
34
What were the advantages of a Single Stage Competitive Tender?
* Competitive tension * Cost certainty * Opportunity to assess design options
35
What were the disadvantages of a Two Stage Competitive Tender?
* No fixed contract sum at first stage * Reduced commercial tension in the second stage
36
What were the advantages of a Negotiated Tender?
* Earliest completion date * Client confidence in the preferred Contractor
37
What was a key disadvantage of the scope reduction option?
Compromises the brief and may reduce perceived value or satisfaction for stakeholders.
38
What was an advantage of the value engineering exercise?
No compromise on functionality and no impact on BREEAM.
39
What did the author learn about BREEAM requirements?
The importance of understanding BREEAM requirements for office fit-out projects.
40
Fill in the blank: The author's approach to tendering strategies was aligned with the Client's _______.
key drivers
41
True or False: The negotiated tendering approach usually offers the longest programme.
False
42
What is the role of RICS Rules of Conduct in the author's professional practice?
To ensure fairness and transparency throughout the procurement process.
43
What were the main activities during the RIBA Stage 1?
* Project brief and budget cost plan prepared * First stage competitive tender awarded
44
What did the Client focus groups aim to achieve during RIBA Stage 1?
To confirm the Client's key objectives.
45
What was the purpose of the VE meeting arranged during RIBA Stage 4?
To assist the cost team in updating the project budget.