What is an insurance “excess”?
Amount the insured must pay towards cost of claim, agreed in advance.
Why does the value that is insured need to be regularly updated?
Insured value can be index-linked for simplicity, but should be updated to reflect current market building costs, ensuring full value is insured.
Explain what you have done as PD on this project
What is in the H&S file?
Info that may be relevant to subsequent projects, and maintenance, to ensure their H&S.
- Locations of wiring, pipes, waste
- Details of some materials/products used, eg. insulation, decking
- Fire stopping and passive fire protection measures
- Balcony warranty
What was your understanding of Approved Document B that made you think timber could be used above 11m?
Section B4, “External Fire Spread”, requirement B4.(2) of the Building Regulations 2010:
- Regulation 7(2) says “materials which become part of an external wall… are of Euro classification A2-s1, d0 or A1”
- Regulation 7(3) says “(2) does not apply to:… (j) window frames and glass”.
Applies to “relevant buildings”.
What are “relevant buildings” in ADB?
A building with a storey (not inc. roof plant)at least 18 metres above ground level… AND contains one or more dwellings” (also “institution” or “room for resi purposes”)
What is the Euroclass rating of timber?
Untreated timber is Euroclass D, s2, d0. Treated can bring it up to C.
What was the date of the FRA for this building? How often to update it?
May 2019.
On updating it, GUIDANCE set out in “Fire safety in purpose-built blocks of flats” (2011)
How had the PIR foam contributed to the fire? Is it that flammable?
LFB report specifically states “Many balconies have combustible materials as part of their construction… so if a fire starts it can spread quickly.”
PIR foam (Celotex GA4000) has Euroclass F rating (“Easily flammable” under BS EN 13501-1)
Why did you advise a MW contract?
Why did you not use JCT Intermediate contract?
Could have done and was alternative suggested on JCT contract selector.
However felt the additional detail within was not necessary - no Bill of Quantities on project, no detailed contract provisions needed.
What was your advice regarding paying the 50% deposit?
What is the clause in the JCT MW that deals with interim payments? What does it say about deposits?
If you had advised your client against paying deposit, would there have been a Key Issue?
Yes but different – contractor may have claimed a variation if they incurred a £22k loss and had to order different windows, and loss/expense if there was a delay. Key Issue may be, “is it a valid variation/EoT”?
What was your advice regarding the liability of the Approved Inspector if they had incorrectly ‘passed’ the plans?
Negligence – they could pursue them in the courts for costs incurred due to plans being incorrectly passed in March.
What was the U-value of the original PIR insulation?
50mm = 0.44 W/m2K
70mm = 0.33 W/m2K
So, overall probably close to 0.35 W/m2K
What U-value did your 60mm to 30mm HARDROCK provide?
60mm = 0.64 W/m2K
How thick did the HardRock need to be to match the U-value of the original PIR?
Around 110mm (taking into account 70mm drop to 50mm of the PIR)
What would the U-value have been for Option 1, Biohm Mycelium?
Unknown as it did not come in a standard thickness, however to match the original PIR U-value of 0.35, it would had to have been around 85mm.
What would the U-value have been for Option 2, Foamglas Invatherm?
At 100mm, would be 0.43 W/m2k.
Were there any other options?
What “significant, frequent” changes have occurred to Approved Document B in “recent years”?
Which approved documents are relevant to the windows/doors?
L - Conservation of fuel and power
M - Access to and use of buildings
K - Protection against falls, collision and impact
F - Ventilation (be careful with this apparently?)
What did you do under role of CA on this project?