What is meant by “contract administration” in construction?
It is the process of managing and implementing the contract between the employer and contractor to ensure each party fulfils its obligations under the contract terms
What is the main purpose of contract administration under JCT Design & Build 2016?
To ensure the contract is carried out in accordance with its conditions — including time, cost, quality and procedural requirements — through proper notices, certification and record-keeping.
What are the key functions of the Employer’s Agent under JCT D&B?
To administer the contract on behalf of the employer by issuing instructions, assessing payments and extensions of time, and certifying completion while acting fairly and independently
What are the main contract documents within the JCT D&B 2016?
Articles of Agreement, Contract Particulars, Conditions, Employer’s Requirements (ERs), Contractor’s Proposals (CPs), and the Contract Sum Analysis.
Explain the relationship between the Employer, Employer’s Agent and Contractor.
The Employer contracts directly with the Contractor; the Employer’s Agent acts as the Employer’s representative and administrator for issuing instructions and certificates.
What is an instruction under JCT D&B, and who issues it
An instruction is a formal direction issued by the Employer’s Agent to the Contractor requiring a change or clarification permitted by the contract.
What constitutes a variation under JCT D&B 2016?
A variation is an instructed change to the Employer’s Requirements that alters the design, quality, quantity or sequence of the works and may entitle cost and/or time adjustments.
What is the procedure for interim payments under JCT D&B?
The Contractor submits an application; the Employer’s Agent issues a Payment Notice by the due date; payment is made by the final date unless a Pay Less Notice is served.
What are Relevant Events and Relevant Matters?
Relevant Events relate to time entitlement (e.g., weather, variations); Relevant Matters relate to cost entitlement for loss and expense.
What is Practical Completion and why is it significant?
It is the stage when the works are complete for their intended use; at that point liquidated damages cease, retention is released, and the defects liability period begins
What key notices are required under JCT D&B 2016?
Examples include payment notices, pay less notices, extension-of-time applications, loss and expense claims, instructions and completion certificates.
What are the implications of failing to issue a payment notice?
Under the Housing Grants, Construction and Regeneration Act 1996, the amount applied for by the Contractor becomes payable by default if no notice is issued on time.
What certificates are issued during the contract life cycle?
Certificates for interim payments, Practical Completion, Non-Completion, Making-Good Defects, and the Final Certificate
What is the process for determining an Extension of Time?
The Contractor notifies a Relevant Event; the Employer’s Agent reviews evidence and issues a revised completion date if entitlement is established.
What is the purpose of the retention mechanism?
Retention protects the Employer by withholding a percentage of payments to ensure defects are rectified and works completed satisfactorily
What are the main duties of the Contractor under JCT D&B 2016?
To complete the works in accordance with the Employer’s Requirements and Contract Documents, comply with all instructions, and assume design liability where required.
What is the difference between the Employer’s Agent and the Contract Administrator under traditional JCT contracts?
The CA acts as an independent certifier in traditional contracts; the EA in D&B represents the Employer but still acts fairly when certifying matters.
How is design responsibility allocated under JCT D&B
The Contractor is responsible for design and construction based on the Employer’s Requirements and their own Contractor’s Proposals.
What other standard forms of contract are you aware of outside JCT?
NEC 4 Engineering and Construction Contract, ICE conditions, FIDIC, PPC 2000 and JCLI are commonly used in civil engineering and international projects.
How does NEC 4 differ in philosophy from JCT D&B 2016?
NEC is written in plain language, emphasises collaboration and early warning management, while JCT is more traditional and reactive with separate certification roles.
What is Loss and Expense under JCT Design & Build 2016?
“Loss and Expense” is additional cost incurred by the contractor due to events for which the employer is responsible, causing disruption or delay to the regular progress of the works.
What is a relevant event and what are the types of events ?
Relevant Events – Time Entitlement
Relevant Events are the causes of delay that may entitle the contractor to an Extension of Time (EoT) but not automatically additional cost.
They protect the contractor from liquidated damages when the delay is beyond their control.
The main Relevant Events include:
Variations instructed by the Employer’s Agent.
Late issue of instructions or information from the Employer.
Exceptionally adverse weather conditions.
Strikes or civil commotion.
Loss or damage due to specified perils (fire, flood, etc.).
Statutory undertakers’ delays.
Delay in giving possession of the site.
Employer’s suspension of the works.
Any impediment, prevention, or default by the Employer.
Force majeure.
Outcome: Contractor receives more time, not necessarily more money
What is a relevant matter and what are the types of events ?
Relevant Matters are the employer-risk events that cause disruption or prolongation, entitling the contractor to recover proven additional costs (loss and expense).
The main Relevant Matters include:
Variations instructed by the Employer’s Agent.
Failure by the Employer to give possession or access on time.
Late instructions, information, or decision by the Employer.
Suspension of the works by the Employer.
Delay caused by nominated subcontractors or direct contractors.
Impediment, prevention, or default of the Employer.
Outcome: Contractor receives money, but only when actual loss is demonstrated and properly ascertained.
What are the available JCT contract Suites and when would you use them ?
he JCT suite provides standard forms to suit different procurement routes, project scales, and risk profiles:
JCT Home Owner Contracts – for small domestic works where the client is a private individual; simple language and minimal administration.
JCT Minor Works (MW) – for straightforward, low-risk projects where the design is provided by the employer’s consultant; typically below £1 million.
JCT Intermediate Building (IC) – for medium projects requiring more detailed provisions, schedules of rates, and partial contractor design; roughly £1–5 million range.
JCT Standard Building Contract (SBC) – the traditional form for larger, complex projects with full consultant design and separate architect/CA administration; often £5 million +.
JCT Design & Build (DB) – used where the contractor takes single-point responsibility for both design and construction; ideal for clients wanting cost certainty and simplified administration.
JCT Major Project Construction (MP) – a streamlined design-and-build contract for experienced clients on high-value projects (typically £20 million +).
JCT Management Building Contract (MC) – where a management contractor engages trade contractors on the employer’s behalf, suitable for large, multi-package schemes.
JCT Construction Management (CM) – where the employer contracts directly with trade contractors and appoints a construction manager to coordinate them; used for fast-track complex builds.
JCT Measured Term (MTC) – for maintenance, repair, or rolling programme works over a period rather than a single project.