Why did you choose a design and build contract for the Link Bridge?
Why did you choose a two-stage procurement route for the Link Bridge?
What other contracts could have been used? Why wasn’t a management contract used?
Design would be the responsibility of the client, and I wanted to protect my clients interests by harnessing the experience of the contractor into the design. It is not simply the benefits of stick vs unitised, by how methodologies such as scaffold hoists, internal waste routes, cranes etc affect the live building.
In addition, the JCT PCSA is only intended for use with the D&B, standard, major projects and intermediate contracts.
Key pros and cons of stick vs unitised?
Did you undertake any normalisation at tender?
From a programme perspective, we provided a target practical completion date, in which all tenderers provided compliant programmes.
How would you ensure parity amongst tender returns?
Although all programmers could be compliant, some may have greater periods off site and therefore less disruption, some may have inherently higher prelim costs such as using a crane. If all tenders bid on a set methodology, parity of analysis could be achieved, but optimal solutions could be proposed as a second option.
What are the components of a PCSA?
Why use a PCSA?
Why use a PCSA over an LOI?
An employer may need to involve a contractor in a project before it is ready to sign a building contract. This is sometimes generically known as early contractor involvement (ECI). Two common types of agreement between an employer and a contractor in these circumstances are a letter of intent and a pre-construction services agreement (PCSA).
What is the difference between a letter of intent and a comfort letter?
What part of the contract were the stand down days detailed in?
Schedule of Amendments
What was the weighting of tender analysis?
60% commercial 40% technical
Give me examples of the components of tender analysis
JCT and change control – how was the change in scope instructed (as PCSA – allows instructions)?
What PCSA document was used?
JCT PCSA 2016
How do you run an inclusive meeting?
What were the key objectives?
How were the options in your case study presented?
formal paper as part of my weekly client meeting
How did you create the stakeholder map?
liaised with colleagues that were already working within the building, discussed with my client who were the key business leaders on each floor, and the more obvious stakeholders such as H&S and security. – Regularly reviewed and updated stakeholder map.
What is your role under CDM?
Advise my client and make them aware of their duties.
CDM Client duties:
- Appoint a Principal Contractor and Principal Designer
- Allowing sufficient time and resource for each stage of the project
- Ensure that the PD/PC carry out their duties under CDM
- Ensure that the appropriate documentation is in place and provided (PCI, CPP, H&S File)
- For notifiable projects (last longer than working 30 days and involves more than 20 workers at any one time, or the work exceeds 500 individual worker days), the client must notify the HSE through an F10 notification form
How would you prioritise stakeholders on your project?
following a stakeholder mapping exercise, understand who will have the most influence. If high, regular communication, keep them informed and understand their needs and individual requirements (site visits, reports etc).
Components of stakeholder management plan?
How would you deal with tender errors?
nder the JCT Tendering Practice Note 2017, there is alternative 1 and alternative 2. Alternative 1 is where the correction of the tender price is not permitted, and alternative 2 is where the correction of the tender price is permitted. The tenderer must be made aware of the error, and confirm or withdraw under Alternative 1. Under Alternative 2, they can confirm/withdraw, or have the opportunity to amend. If withdrawn, the endorsement should be signed by both parties, if amended under Alternative 2, a letter should be attached to the tender acceptance.
Examples of project finance?