What is the benefit of appointing a contractor to manage VE/Scope Reduction?
Utilizing a contractor can enhance the effectiveness of cost-saving strategies.
Explain the impact on competitive pricing by switching from Single to Two-Stage.
Unliked a single-stage where works are competitively tendered upon completion of design.
There is an element of reduced competitiveness, as contractor is already engaged.
Competitveness is replaced by negotiation.
Intention would be to still use open book tendering 3 suppliers per package.
Two-stage tendering often leads to negotiation rather than competitive tendering.
Would you share the cost plan with the contractor if appointed?
RICS guidance stresses open-book collaboration under the PCSA.
Did you see the Two-Stage option as viable for reducing costs?
Yes - Part of there PCSA was obviously to facilitate with cost reduction.
Also - By de-risking the project & drive value. Which can reduce overspend through post contract change.
Drive further value through VE/Buildability
This is an approach that’s largely favoured due to the time constraint on the project.
Two-stage can unlock savings through de-risking, VE, early site start, and reduced program.
What was the contractor’s role under the PCSA?
The contractor’s role includes identifying long lead items and potential procurement of enabling works.
What was the contractor’s role under the 2nd Stage?
This stage focuses on finalizing the financial aspects and preparing for construction.
How could you demonstrate cost-saving ability for the Two-Stage Approach?
Benchmark reports show two-stage procurement results in fewer disputes and more predictable final accounts.
How could you save time under the Two-Stage approach?
Early engagement can help mitigate delays.
What sort of cost build-up would you expect for the PCSA?
These elements contribute to the overall cost structure of the PCSA.
How would you appoint under a Negotiated approach?
Sharing information helps validate the proposal.
What other forms of contract/procurement could have been appropriate?
Each method has its own advantages and disadvantages regarding cost certainty and client control.
Why was the Two-Stage approach ultimately rejected?
The decision was influenced by the need for predictable costs.
What is the difference between a single stage strategy vs two stage?
The two-stage approach allows for collaboration during the design phase.
How could you seek competitiveness at the 2nd stage?
Transparency in the tendering process can enhance competitiveness.
At what stages would you typically tender on at single vs two stage tendering?
How were the benefits of having a contractor onboard still accounted for despite the approach not going forward?
Effective strategies can still yield positive outcomes even without proceeding with the contractor.
Could you provide a rough estimate for the PCSA?
This estimate can range from 75k to 225k.
How long did you expect the PCSA to last?
Around 8-12 weeks
This timeframe is typical for the completion of a PCSA.
How did you see the management occurring between you and the contractor in terms of cost reductions?
*Open-book Collaborative approach (Tendering Strategies 1st Edition)
* Contractor proposes practical cost saving solutions; These would be reviewed with the team/ approved/rejected (aligned to the clients profile) - validated commercially by me as the QS.
* Implement these into the Stage 4 cost plan.
Alignment with client objectives is crucial for effective management.
Why didn’t you propose a Design & Build?