What are the 5 key elements of CDM?
When is a project notifiable?
If it lasts more than 30 working days AND has more than 20 workers at the same point
OR
It has more than 500 person days
Under CDM what must all projects have?
Under CDM what must all multi-contractor projects have?
Who are the ‘dutyholders’ under CDM?
What duties does the Commercial Client have under CDM?
A Commercial client has work done in connection with their business (whether for profit or not)
What duties does the Domestic Client have under CDM?
A Domestic Client has work carried out NOT in connection with a business.
-