CDT Test from CSI Flashcards

(29 cards)

1
Q

The project team consists of:

a. design, contractor and supplier teams
b. owner, design and contractor teams
c. owner, design, contractor and supplier teams
d. owner, contractor and supplier teams

A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The Owner is responsible for:

a. providing project funding
b. inspecting the construction
c. commissioning the HVAC system
d. hiring the subcontractors

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

During which facility life cycle stage does the A/E review the Owner’s program and budget?

a. Project Conception
b. Design
c. Construction Documents
d. Construction

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the difference between Drawings and Specifications?

A. There is no difference between the Drawings and Specifications.
B. Specifications indicate products quantitatively and Drawings indicate products qualitatively.
C. In a typical Design-Bid-Build project specifications identify what sections Subcontractors are responsible for.
D. Drawings indicate products quantitatively and Specifications indicate products qualitatively.

A

D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The Drawings include the following information:

A. Installation and performance requirements.
B. Physical properties and standard of workmanship.
C. Location, identification, dimension, size, and details.
D. Warranty and submittal requirements.

A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What type of Drawings would include details and schedules?

A. Construction drawings.
B. Conceptual drawings.
C. Schematic design drawings.
D. Shop drawings.

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The Specifications include the following information:

A. Quantity, capacity, and location of products and materials.
B. Physical properties, chemical constituents, and performance requirements.
C. Detailed drawings of assemblies.
D. Material and equipment schedules.

A

B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which type of information is found in the Specifications?

A. Location of where products are used.
B. Identification.
C. Standards of workmanship.
D. Connection details.

A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The MasterFormat groups include:

A. Specifications and Process Equipment.
B. Procurement and Contracting Requirements and Specifications.
C. General Requirements and Facility Services.
D. Site and Infrastructure and Procurement and Contracting Requirements.

A

B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

SectionFormat describes:

A. Guidelines for the display of specification text.
B. The recommended section titles to use.
C. How many parts there are in sections.
D. What submittals are to be prepared for a product.

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The Project Manual includes:

A. Specifications, addenda, and conditions of the contract.
B. Project forms, revisions, and modifications.
C. Procurement requirements, contracting requirements, and specifications.
D. Contract drawings and resource drawings.

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

General and Supplementary Conditions should be prepared by and/or have the approval of:

A. Owner and A/E.
B. Owner including Owner’s counsel.
C. A/E and Contractor.
D. Contractor and subcontractors.

A

B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The Supplementary Conditions:

A. Do not contain contractual/legal provisions.
B. Are not part of the Conditions of the Contract.
C. Include contractual/legal requirement provisions that supplement the General Provisions.
D. Modify General Conditions to suit specific project requirements.

A

D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Revisions to the Contract Documents are done at what time in the project process?

A. During the bidding/negotiations and construction phases.
B. After project closeout.
C. During the design phases.
D. When the bids are due.

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

In what Division would you find specifications for roofing?

A. Division 02
B. Division 07
C. Division 14
D. Division 26

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The Procurement Phase is:

A. The transition from design to construction.
B. When the Owner tells the Contractor how much is in the budget.
C. The time when the documents are prepared.
D. The end of the design process.

17
Q

Addenda are used to accomplish all of the following except:

A. Increase the scope of the work.
B. Change the quality of the work.
C. Correct unforeseen field conditions in the work.
D. Add additional qualified products or approved substitutions to the specifications.

18
Q

The Owner may obtain goods for the project or maintenance using:

A. Requests for proposals and purchase orders.
B. The construction procurement documents.
C. A list of items prepared by the subcontractor.
D. Manufacturer’s recommended specifications.

19
Q

What written document is used by the A/E to describe a project during the Design Development phase of a project?

A. Preliminary Project Description
B. Agreement
C. Outline Specifications
D. Project Manual

20
Q

Cost estimating methods include the following except:

A. Unit price
B. Bid pricing
C. Assemblies/systems
D. Order of magnitude

21
Q

Preconstruction submittals include

A. bonds, schedules, and certificates of insurance.
B. samples, mockups, and coordination drawings.
C. submittal schedule, shop drawings, and samples.
D. test reports, construction schedule, and design data.

22
Q

What is a guarantee?

A. A written agreement that extends the product’s lifespan beyond its expected use.
B. A commitment provided by a party assuming responsibility if a product or design fails to perform.
C. A financial commitment from the owner to cover future maintenance costs.
D. A promise that a project will be completed on time, regardless of unforeseen conditions.
E. A promise that goods sold or installed meet certain standards or expectations, even if not explicitly stated in the contract.

23
Q

The contract documents include the Agreement, General Conditions, Supplementary Conditions, Revisions, and other procurement-related documents such as Instructions for Procurement and Procurement Forms.

A. True
B. False

24
Q

Which type of document is most likely required if the construction site is located near historical land, landmarks, or artifacts?

A. Geotechnical Investigation
B. Archeological Study
C. Environmental Study
D. Existing Facility Evaluation

25
What incentive is commonly used to ensure timely completion of a project? A. Performance Bonds B. Retainage C. Liquidated Damages D. Change Orders E. Substantial Completion F. Addenda
C
26
What is the most likely consequence for a design professional if uncoordinated contract documents result in significant project delays and increased costs? A. Termination of the contractor B. Professional Negligence Claim C. Revised payment terms for the owner D. Automatic approval of change orders
B
27
Omni, Uni, and Master are: A. Taxonomical B. Compositional
28
When should an alternate be used in a construction project? A. When the contractor requests clarification on project specifications during the bidding process B. When the design team wants to suggest optional materials for the contractor to choose from C. When an item needs to be priced separately because it might be added or removed from the scope D. When the owner wants to modify the project timeline but keep the same scope of work E. When the architect needs to reissue construction documents due to design changes
C
29
What is a schedule of values of a project? A. A financial summary detailing anticipated expenses for each phase of the project. B. A timeline for project completion that includes milestones and deadlines. C. A list of materials required for construction, including quantities and suppliers. D. A detailed breakdown of the contract sum, allocating costs to each division of work to track progress and support payment applications.
D