OPTIMUM HOURLY PRODUCTION RATE
CYCLES PER HOUR X VOLUME PER CYCLE
BANK CUBIC YARDS (B. CY)
SOIL RESTING IN ITS NATURAL, UNDISTURBED STATE
LOOSE CUBIC YARD (L. CY)
WHEN SOIL IS EXCAVATED OR DISTURBED FROM NAT. STATE, IT SWELLS, INCREASING ITS VOLUME.
COMPACTED CUBIC YARD (C. CY)
WHEN SOIL IS COMPACTED IT SHRINKS, DECREASING IN VOLUME.
LOAD FACTOR
BANK VOLUME / BANK VOLUME + SWELL %
HUMAN EFFICIENCY FACTOR
50 MINUTES OF PRODUCTIVE WORK PER HOUR
EFFICIENCY FACTOR
MINUTES WORKED PER HOUR / 60 MINUTES=50/60=.83%