When a Change is request by a SH or a Change is being discussed. Do you update the Change log or Issue log first?
You do NOT update Issue Log.
You update the Change log first.
What is the difference between Creating/Writing a CR and Documenting a CR?
What is Creating/Writing a CR?
Formally submitting a proposed change to the CCB or your Sponsor in form of a 1-Pager AFTER the impact analysis is done.
What is “Documenting” a CR?
This is the first step when a change is verbally proposed by a stakeholder. Generally, this means updating your ‘change log’ document with this change as a ‘new request’
If you recieved a change was verbally communicated to you. What does documenting this change in the change log do to the change control or configuration control systems?
Documenting a change(Change log), in itself updates the change/config management systems.
The change log is directly tied into them.
Then you can move on to next ICC steps: Impact analysis->CCB Review
Learning Point 2 ICC
What do you do with a verbal change request?
What is the central change history repository for the life of a project?
The change log: contains the history of all changes and their statuses.
Can you change baselines or the PMP before officially approved?
“Before the baselines are established, changes are not required to be formally controlled by the Perform Integrated Change Control process.
Once the project is baselined, change requests go through this process”
Agile ICC- CCB & SCRUM
What is CCB in SCRUM(Agile)?
Agile ICC- CCB & SCRUM
How is the CCB different in SCRUM vs Traditional Predictive project?
Agile ICC- CCB & SCRUM
In SCRUM how is In scope and out of scope changes handled differently?
Agile ICC- CCB & SCRUM
What
Agile ICC- CCB & SCRUM
What are the 7 key roles in CCB for SCRUM?
2.Project Assistant: Responsible for documenting changes and serving as a secretary to the board.
3.Project Assistant: Supports PM handling admin tasks: Documentation, record keeping, scheduling meetings, maintain project calendars, send SHs updates, prepping reports, tracking progress, acts as secretary during CCB meetings taking notes and organizing docs.
* Example: Records minutes of the CCB meeting and updates the project plan. difference from PM? ON agile team?
5.Board Members: Team members who evaluate and vote on changes.
* Example: A technical lead assessing the impact of a new software feature on project scope.
6.Initiator: Proposes the change and explains the need for it.
* Example: A developer who suggests modifying the codebase to enhance performance.
7.Reviewer (two types):
1.Evaluates the impact of the proposed changes on scope, schedule, and cost.
* Example: Conducts analysis to determine if a change will delay project milestones.
2.Verifies if the approved changes were implemented correctly.
* Example: Reviews project outputs after change implementation to ensure accuracy.
Agile ICC- CCB & SCRUM
What’s the difference between a Change Control Board and a Change Advisory Board?
CCB: Primarily handles changes within specific projects.
* Composition: Can include project stakeholders like the PM, key team members, and sometimes external stakeholders or sponsors, May include SME’s relevant to project scope..
* CCB Example: A project team proposes adding a new feature to the project scope. The CCB assesses the impact on the timeline, budget, and resources before deciding whether to approve or reject the change.
CAB(Chg Advisory Board): Manages changes across the service lifecycle, including emergency changes. Evaluates the technical, operational, and business impact of changes(Strategic level of change on the business[Ongoing services or business operations].
* Scope: Review changes that affect multiple systems or the broader service environment, not limited to one project.
* Decision Making Focus: Ensure changes won’t negatively impact ongoing services or business operations.
* Strategic level Change Management: Works at a strategic level to ensure stability and availability of** services across the organization.**
* Environment: Common in IT orgs. Often deals w/ changes that affect multiple teams or departments.
* Composition: Usually includes reps from multiple areas of org, such as IT, business operations, and customer service.
* Can include senior leadership, service managers, and technical leads to ensure a broad view of the impact of changes.
* Focus on Emergency Changes: managing and approving emergency changes in IT environments.
* CAB Example: An organization needs to upgrade a database server that multiple departments rely on.
* The CAB reviews the potential risks to other services, downtime implications, and plans a maintenance window.
Agile ICC- CCB & SCRUM
What are the SCRUM Change Management steps?
1.Initiate CR:Customer/SH or team member request CR.
* Output: Change request USER STORY: CR takes the form of a user story
2.PO Evaluates CR: PO reviews CR to assess its value, priority, and alignment w/ project vision and whether to add to the scope(PBL).
* Yes: Proceed to the next step.
* No: Reject or defer CR
4.BL Refinement(Grooming): Scrum Team discuss new PBL Item
* Actions: Breakdown CR into smaller USs
* Team is self empowered and decides what it would take to do this change if they have the technical knowledge to do so. Not the PM or SM.
* Discuss and estimate effort (Story points)
* Team self empowered and have the experience to know how much effort it would take to do change.
Identify Dependencies or technical requirements for implementing the change.
* Adjust the priority based on team feedback.
5.Sprint Planning: Is CR prioritized high enough to include in the sprint backlog?
* Yes: CR added to SBL during Sprint planning
* NO: Remains in PBL for consideration in future sprints.
6.Sprint Execution:
* Development: Scrum Team begins to work on SBL, which may include CR(User story)
* Daily Scrum: During Daily Standups, the team discusses progress, blockers, and adjustments, if needed for CR.
7.Sprint Review:
* Showcase: at end of sprint in Review, team demos completed product increment, including the CR by the customer
* SH Feedback: SH including customers provide feedback on change. If additional adjustments are needed, they are added back to the PBL for future considerations.
How do we incorporate change activities into agile?
If project having issues and the solution requires more budget can we request more funding from Sponsor?
Requesting additional funding from the sponsor without going through the formal change control process can lead to uncontrolled scope and budget changes.
* The project sponsor may be involved in approving the change, but it’s essential to involve the CCB, requesting additional funds should typically follow the submission of a change request to the CCB.
Change Management(not ICC) but Org level
What are the 3 Phases of Change management?
https://www.pmi.org/learning/library/change-management-understanding-human-dynamics-6252
ADKAR: Org Change Management Steps
Put them in order and explain each
A.Knowledge
B. Desire
C. Awareness
D. Reinforcement
E. Ability
**ADKAR® Model
Jeff Hiatt developed the ADKAR® Model which focuses on five sequential steps that individuals
undergo when adapting to change:
4.Ability: Demonstrate new skills and behaviors
5.Reinforcement: Make change stick. Supports the sustainment of the change. This can include rewards, recognition, feedback, and measurement.