What is cost estimation?
Probable total cost of a future activity
What is the purpose of cost estimation? (part A)
What is the purpose of cost estimation? (part B)
What is the purpose of cost estimation? (part C)
8. Preparing a payment schedule
What are the applications of approximate estimate?
1) Evaluating project feasibility
2) Evaluating cost of proposed design modifications
3) Establishing a preliminary budget for control purposes
4) Screening a number of alternative projects
How is an approximate estimate prepared?
Use only basic criteria such as :
Output
Total sqft
Number of units etc’
When is it good or not good to rely on an approximate estimate ?
Good:
1) Evaluation of design alternatives
2) Presentation of preliminary construction estimate to the owner
Not good:
Bid purposes
List the 4 components of a detailed estimate
1) Estimated cost (materials, labour, equipment, subcontract work)
2) General expenses (Overhead, tax, insurance)
3) Contingency (Risk analysis)
4) Profit ( Top level mgmt)
What is the basic approach to prepare detailed estimates?
What are the components of bid estimate (detailed estimate)?
Bid price = Cost estimate +Contingency +General exp + Profit
Name factors of contingency
What is traditional (design - bid - build) delivery?
The project is fully design before work begins
What is design-built delivery?
A single organization responsible for design and construction
What is construction management delivery?
Facilities overlap between project stages. The main objective is earlier completion
What is a public-private partnership?
* Private sector will operate at first and then handover the asset to the public sector
Name 3 types of contracts
1) Lump-Sum contracts
2) Cost-plus contracts
3) Unit-price contracts