Acknowledgment - An acknowledgment shows receipt of the message, but not necessarily agreement with the message.
Approval - требуется явное подтверждение
Information Radiators (agile) - e.g. KANBAN with WIP. May include: features delivered/remaining, Risks, Burn charts, Who is working on what, Velocity/Defects metrics, Story maps
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
Project Reporting - types of reports
A
Status report - generally static (relating to a moment in time). Or compare with the perfomance measurement baseline??
Progress report - describes what has been accomplished
Trend report - past performance up to the point the report is created
Forecasting report - looks only in the future
Variance report - compares actual results to performance measurement baselines
Earned value report - integrates scope, cost, and schedule measurements to assess project performance relative to baselines and variances
Progress metrics - reports such as Cumulative Flow Diagrams and burnup charts are used to assess performance
Retrospective findings - used to inspect, adapt, and improve project and team performance
Lessons learned - summarties of lessons learned that may be used immediately on the project or used for future projects