what are the 10 steps of project planning?
S I I A I E -> AR RP EP LP
- Select project
- Identify scope & obj
- Identify infrastructure
- Analyze characteristics
- Identify product & activities
- Estimate effort
- Identify risk
- Allocate resource
- review & publicize
- execute plan
- level planning
what are the 2 main causes of project failure?
____________ is an element of work with expected duration, cost & resources?
activity
____________ is the lowest level of work on a project?
task
what is work breakdown structure?
it is a hierarchal & incremental decomposition of a project into phases.
WBS uses __________ or __________ format?
list & describe the 3 types of WBS.
list & describe techniques of WBS.
what are basis of WBS?
define scheduling.
is a calendar that links tasks that need to be done with resources
what are the primary objectives of scheduling?
parol officer - can ride truck
- least cost
- least risk
- best time
what are secondary objectives of scheduling?
significant other - can eat apples
- communication
- alternate scheduling
- effective resource allocation
what are the steps to building a schedule?
are id computerscience oR are optimized
- allocate resource
- identify dependencies
- create the schedule
- reconcile the schedule
- add review meetings to schedule
- optimize schedule
when is a task said to have dependencies?
when it requires an activity, resource or work product that is required by a d/t task
list type of dependencies
(predecessor, current dependent)
- FS , SF (rare) , FF, SS
when creating a schedule, most use ____________ ?
gantt chart
a gantt chart shows ______, _______ & ________.
tasks, dependencies & milestones
allocating resources to tasks on critical path is done during _________ stage of scheduling?
optimization
what are techniques of scheduling?
list types of network diagrams.
__________ was developed in 1950’s?
__________ is a graphical representation of tasks that need to be completed for a project?
network diagram
what are the 2 classical formats of a network diagram?
on a network diagram, each task is labeled with _______ & _______?