What is the focus on, when working on De-Energized Lines and Equipment?
Protecting the workers in case the line becomes energized unexpectedly.
What is installing Protective Grounds and Bonds designed to do?
- Limit the current flow and voltage drop across the lineworker’s body.
What must be done to ensure proper installation of Protective Grounds and Bonds?
Each step must occur in the correct order and the entire crew should work together to help ensure safety of all employees and the public.
What does every job begin with?
A Job Briefing or (Tailboard)
How does a tailboard improve the effectiveness of the grounding process?
Identifies:-The locations of all possible energy sources
What are the 5 Steps to properly ground a line?
When completing the Identify Step what does it entail?
Identify the section of line to be cleared by using circuit maps, cable tags, or other information sources. Consult with system operator f there is any confusion about what is being cleared, and when and how it will be done.
When completing the Disconnect Step what does it entail?
Disconnect the section from all possible energy sources of electrical energy. This may involve opening switches, standing off cable, removing jumpers, or other tasks. All devices in the path of the flow of power are opened, checked open, locked if possible, and tagged.
When completing the Test Step what does it entail?
Test the line for presence of voltage. Do not contact the line without first testing it, even if you are “sure” the crew did everything right during the clearance process.
When completing the Clean Step what does it entail?
Clean all connection points-including the clamps, conductors, cluster bracket, ground rods, anchors-prior to applying grounds. This minimizes resistance an improves the effectiveness of the grounds.
When completing the Ground Step what does it entail?
Ground the section of line after it has been disconnected, tested, and cleaned-and before employee contact is made. Install grounding components according to grounding scheme and follow the Golden Rule.
What does OSHA require before applying grounds?
TEST ALL LINES AND EQUIPMENT
How should you act when testing the line for voltage?
As if it is energized.
When is the line officially De-Energized?
After you Test and Ground it.
What should you know when using tools to test the line?
What kind of tester should you use?
An approved tester, and verify that it’s working.
What are the industries best practices for using a tester?
What are the common tools used for testing the line for voltage?
- Audible Tester
Essentially, what is a Multirange Voltage Detector?
A Multiple-range field intensity meter, this instrument has a switch for selecting kilovolt ranges.
How does a Multirange Voltage Detector differ from a voltmeter?
It uses the field strength to estimate the line-to-line voltage.
What are some properties of Multirange Voltage Detector?
How does an Audible Tester work?
An electronic instrument that attaches to a live-line tool. The unit is placed close to or in contact with the conductor and will produce and audible warning and flashing light if voltage is detected.
What are some properties of an Audible Tester?
Which of the two is said NOT to be used to test the line for voltage?
Audible Tester