b. conceptual design [Correct. During conceptual design, users develop and
evaluate appropriate design alternatives.]
e. a, b, and c [Correct. The conceptual design report guides physical systems
design activities, communicates how management and users’ needs are met,
and helps the steering committee assess system feasibility.]
d. output, file and database, input, program, procedures, controls [Correct.
See Figure 22-2.]
a. scheduled report [Correct. Scheduled reports have a specified content,
format, and delivery time. A monthly payroll register exhibits these
characteristics.]
d. How often should the system produce reports? [Correct. Report generation
frequency is not normally considered during input design. See Table 22-4.]
6. Which of the following is most likely to help improve program development? a. physical model b. IT strategic plan c. walk-through d. record layout
c. walk-through [Correct. During walk-throughs, people associated with
designing the project review it step-by-step so any problems can be identified
and corrected.]
d. Over the life of a system, only 30% of information systems work takes place
during development; the remaining 70% is spent maintaining the system.
[Correct.]
c. acceptance test [Correct. An acceptance test uses real transaction data to
test a new system.]
9. What is the process of discontinuing an old system as soon as a new one is introduced? a. direct conversion b. parallel conversion c. phase-in conversion d. pilot conversion
a. direct conversion [Correct. Indirect conversion, the old system is
discontinued as soon as the new one is activated.]
10. Which of the following describes designing a program from the topdown to more detailed levels? a. hierarchical program design b. top-down program design c. parallel program design d. unstructured program design
a. hierarchical program design [Correct. Hierarchical program design is the
process of programming from the general level to the detailed level.]