Name the 5 mandatory items included in a bid
Guarantee
Certifate from a Surety
Statement of Corporate Ownership
Listing of Subcontractors
Addenda
Name the 5 types of cooperative purchasing systems
Cooperative Pricing
Joint Purchasing System
Commodity Resale System
County Cooeprative Contract Purchasing
State Contracts
Name the (4) types of mistakes done on public works contracts and/or why you would grant a contractor to withdraw their bid
The enforcement of the contract, if actually made, would be unconscionable
The mistake relates to the material feature of the bid
The mistake occurred notwithstanding the fact that the bidder exercised reasonable care in preparation of the bid
The bidder making the mistake is able to get relief by way of withdrawing the bid without serious prejudice to the contracting unit
Name the 5 major methods of vendor selection
Competitive Sealed Bidding
Competitve Contracting
Competitive Quotations
Proprietary Purchases
Emergency Purchases
Responsive vs Responsible
Responsible : Able to complete the contracy in accordance with its requirements
Responsive : Conforming in all material respects
Debarrment
Prior Negative Experience (Not necessarily with self, the WALL, LFN 2024-18)
Maxmimum of 5 years
Lowest Price
The least possible amount that meets all requirements of the request of the contracting agent
Proprietary
Goods or services of a specialized nature that may be made or marketed by persons having the
exclusive right to make or sell them when the need has been certified in writing by the
governing body of the contracting unit to be necessary for the conduct of its affairs
Green Product
Any commodity or service that has a lesser or reduced negative effect on human health and the environment when compared to competing commodities or services
Concession
Granting of a license or right to act for or on behalf of the contracting unit
Threshold for Governing Body to award a fair and open contract
Yes-if over $300 must report to ELEC, but with prohibit them from being awarded non fair and
open if gave over $300 in prior year and during term of contract
True or False
Under Equal Employment Opportunity (EEO) and Affirmative Action (AA) the local unit must name by resolution the Purchasing Agent as the Public Agency Compliance Officer (PACO):
False
- Maintenance/Construction Contracts
- After award, but before signing contract, contractor must submit a project workforce report to the PACO
True or False
Local Unit Energy Savings Investment Program (ESIP) shall be submitted to the BPU for review and approval:
True
True or False
Prior to operating, all local cooperative purchasing systems must be approved by the Division of Local Government Services:
True, renewing every 5 years
True or False
Evaluating criteria and weighing factors in competitive contracting become public record
True-Eventually, only after the decision is made and notice of award is transmitted to governing body
True or False
A “no conflict form” is required to be filled out for competitive contracts by the evaluating commitee
True
True or False
Evaluation team for competitive contracting must file a “no conflict” form before proposals are evaluated
True
True or False
Pursuant to law, one of the reasons for rejection of all bids is that the governing body of the contract decides to abandon the project
True
True or False
In co-op, lead agency certifies funds
False - they do not certify funds, purchasing entity does ***
True or false
Unforeseen circumstances can only postpone, not cancel a bid
True
True or False
All 50 states use some form of the Uniform Construction Code
True
True or False
An item valued below the quote threshold may be sole at private sale
True
True or False
Insurance company is “for-profit” not non-profit
True
True or False
In order to utilize competitive contracting you must have a Purchasing Agent designated or appointed by the Governing Body
True