What are the 5 process groups?
1 - Initiating
2 - Planning
3 - Executing
4 - Monitoring & Controlling
5 - Closing
What are the 10 Knowledge Areas?
1 - Project Integration Management
2 - Project Scope Management
3 - Project Schedule Management
4 - Project Cost Management
5 - Project Quality Management
6 - Project Resource Management
7 - Project Communications Management
8 - Project Risk Management
9 - Project Procurement Management
10 - Project Stakeholder Management
Name the Process Group and Knowledge area for the process(es) listed:
Initiating/Integration Management
Name the Process Group and Knowledge area for the process(es) listed:
Initiating/Stakeholder Management
Name the Process Group and Knowledge area for the process(es) listed:
Planning/Integration Management
Name the Process Group and Knowledge area for the process(es) listed:
Planning/Scope Management
Name the Process Group and Knowledge area for the process(es) listed:
Planning/Schedule Management
Name the Process Group and Knowledge area for the process(es) listed:
Planning/Cost Management
Name the Process Group and Knowledge area for the process(es) listed:
Planning/Quality Management
Name the Process Group and Knowledge area for the process(es) listed:
Planning/Resource Management
Name the Process Group and Knowledge area for the process(es) listed:
Planning/Communications Management
Name the Process Group and Knowledge area for the process(es) listed:
Planning/Risk Management
Name the Process Group and Knowledge area for the process(es) listed:
Planning/Procurement Management
Name the Process Group and Knowledge area for the process(es) listed:
Planning/Stakeholder Management
Name the Process Group and Knowledge area for the process(es) listed:
Executing/Integration Management
Name the Process Group and Knowledge area for the process(es) listed:
Executing/Quality Management
Name the Process Group and Knowledge area for the process(es) listed:
Executing/Resource Management
Name the Process Group and Knowledge area for the process(es) listed:
Executing/Communication Management
Name the Process Group and Knowledge area for the process(es) listed:
Executing/Risk Management
Name the Process Group and Knowledge area for the process(es) listed:
Executing/Procurement Management
Name the Process Group and Knowledge area for the process(es) listed:
Executing/Stakeholder Management
Name the Process Group and Knowledge area for the process(es) listed:
Monitoring & Controlling/Integration Management
Name the Process Group and Knowledge area for the process(es) listed:
Monitoring & Controlling/Scope Management
Name the Process Group and Knowledge area for the process(es) listed:
Monitoring & Controlling/Schedule Management