What process group is Manage project knowledge part of?
Executing
Prior to project authorisation, how might the business decide to select the project?
What are the economic measures that can be used for selecting a project?
What is working capital?
Organisation’s current assets minus its current liabilities
What two types of depreciation exist?
- accelerated depreciation
Who should write the project charter and what is in it?
In the case of a buyer and a seller, BOTH should write the charter
What is in the project mgmt plan?
What is often the cause of change requests?
Inadequate risk mgmt
What is typically the difference between the project mgmt plan and project documents?
Plans are approved by sponsor, documents typically are not
What is a work authorisation system?
A system for the project manager to authorise the start of work packages or activities
What are the inputs to the manage project knowledge process?
What does the monitor and control project work process do?
Aggregates the work performance information from monitoring and controlling knowledge area processes to evaluate how their individual results are impacting the other ares and their plans and the baselines
What should a project manager do if a work activity takes longer than estimated?
Request a corrective action through the change process to make up for the delay (so don’t change the baseline unless strictly necessary)
What is the typical process for making changes?
Note 1: if a reserve has been allocated to a risk, it does not have to go through change control
Note 2: the project manager may be able to approve some changes, but does that affect project mgmt plans, baseline, charter likely via sponsor or change control board
What is the internal rate of return?
The internal rate of return is a measure of an investment’s rate of return. The term internal refers to the fact that the calculation excludes external factors, such as the risk-free rate, inflation, the cost of capital, or various financial risks. It is also called the discounted cash flow rate of return.
Who has the primary responsibility to decide if changes to the project charter are necessary?
The sponsor