What is BCWP & ACWP stand for?
Budgeted cost of work performed
Actual costs of work performed
What is the process of front loading? Why is it done?
front loading is achieved by assigning higher costs to early activities, and lower costs to late activities, but keeping the total project cost unchanged. It is a common practice since the GC tends to have a lot of expenditures at the beginning of the project.