Plan Schedule Management process
Answers questions like:
Key output of the Plan Schedule Management process?
Schedule management plan
Schedule management plan
Define Activities process
Taking the work packages created in the WBS and decomposing them into the activities that are required to produce the work package deliverables
When decomposing work packages, how do you know when you’ve decomposed enough?
Activities should be at a level small enough to estimate, schedule, monitor, and control
What happens after you define acitivites, i.e., decompose work packages?
Sequence activities
What do you need to define activities?
When is decomposition used for Define Activities process in schedule management, and for Create WBS process in scope management?
Define Activities
When work packages are decomposed into activities to produce them
Create WBS
When deliverables are decomposed into smaller deliverables
Rolling wave planning
What does the Define Activities process result in?
An activity list, which includes all activities required to complete the project, and details regarding project activities
Sequence Activities process
Taking the activities and sequencing them in the order in which the work will be performed
What does sequencing activities result in?
A network diagram
What does a network diagram represent/show?
How are most network diagrams created today?
Precedence Diagramming Method (PDM)
Different types of logical relationships between activities
Finish to start (FS)
Start to start (SS)
Finish to finish (FF)
Start to finish (SF)
Types of dependencies
Mandatory dependency (hard logic)
Inherent in the nature of work, or required by a contract
Discretionary dependency (preferred, preferrential, or soft logic)
External dependency
Based on the needs or desires of a party outside the project (for example, government, suppliers, etc.)