What causes project trade-offs?
Shifts in the relative importance of criterions related to cost, time, and performance parameters
• Budget-Cost
• Schedule-Time
• Performance-Scope
Managing the Priorities of Project Trade-offs
1. Constrain a parameter is a fixed requirement 2. Enhance optimising a parameter over others 3. Accept reducing (or not meeting) a parameter requirement
Performance, cost and time relationships
How to shorten a project that is too long?
2. Add more resources among critical path activities
To reduce duration, to which activity on the critical path do we add resources?
the activity with the SMALLEST scope
How far can an activity be reduced?
How to reduce cost?
Non-critical activities can be “relaxed” (stretched)
To reduce cost, which activity on the critical path do we relax first?
non-critical activity with the highest cost
Variability of Activity Duration
the range of possible activity durations can be presented as a distribution curve
PERT Technique
what does it stand for?
Program
Evaluation
and Review
Technique
what is the PERT technique?
PERT Technique: Durations is based upon three estimates for each activity
a = optimistic m = most likely b = pessimistic
pessimistic duration (b)
exclude highly unlikely events
PERT Technique: Compute Expected Time (te) of an activity
te = (a + 4m + b)/6
PERT Technique: Compute Mean Project duration
Sum of te values of activities on the critical path = Te
PERT Technique: compute the standard deviation for every activity
o = (b-a)/6
V=o^2
V = [(b-a)/6]^2
Shortcomings of PERT
Managing Multi-project Scheduling
Multi-project Scheduling Problems
• Overall project slippage
- delay on one project create delays for other projects
• Inefficient resource application
- the peaks and valleys of resource demands create scheduling problems and delays for projects
• Resource bottlenecks
- shortages of critical resources required for multiple projects cause delays and schedule extensions
Critical Chain Method
How do contingency reserves get wasted?