DISCHARGE BY PERFORMANCE
Overview
1) Time for performance
2) Manner of performance
TIME FOR PERFORMANCE
Overview
1) General rule
2) Time is of the essence
3) Time is not of the essence
4) Time in conditional contracts
TIME FOR PERFORMANCE
General rule
1) S.47:
- within reasonable time.
2) Damansara Realty Bhd v Bungsar Hill Holdings Sdn Bhd:
TIME IS OF THE ESSENCE
Overview
1) The law & scope
2) When is time of the essence - general rule
3) Existence of LAD clause
4) Waiver
5) Acceptance of performance other than time specified
6) Failure to perform
TIME IS OF THE ESSENCE
The law & scope
1) The law:
- S.56
2) Scope - Sim Chio Huat v Wong Ted Fui:
TIME IS OF THE ESSENCE
When is time of the essence - general rule
Tan Ah Kian v Haji Hasnan:
TIME IS OF THE ESSENCE
When is time of the essence - existence of LAD clause
1) BTS Sdn Bhd v M-Concept Sdn Bhd (FC):
- when there is LAD clause, it points to time not being of the essence.
2) cf. Chye Fook v Teh Teng Seng Realty Sdn Bhd:
TIME IS OF THE ESSENCE
Waiver - overview
1) Effect of waiver
2) Silence
3) Continued negotiations
4) Extension of time
5) Extension of time + continued negotiations
WAIVER
Effect of waiver
Sim Chio Fuat v Wong Ted Fui:
WAIVER
Silence
Araprop Development Sdn Bhd v Leong Chee Kong & Anor:
WAIVER
Continued negotiations
Wong Kup Sing v Jeram Rubber Estate Ltd:
WAIVER
Extension of time
Siah Kwee Mow v Kulim Rubber Plantation:
WAIVER
Extension of time & continued negotiations
Wong Kup Sing v Jeram Rubber Estate Ltd:
ACCEPTANCE OF PERFORMANCE OTHER THAN TIME SPECIFIED
Overview
1) the law & scope
2) housing development
ACCEPTANCE OF PERFORMANCE OTHER THAN TIME SPECIFIED
the law & scope
1) The law:
- S.56(3)
2) Scope - Yeo Kim Pong Realty Ltd v Ng Kim Pong:
ACCEPTANCE OF PERFORMANCE OTHER THAN TIME SPECIFIED
housing development
Sentul Raya Sdn Bhd v Hariram Jayaram:
FAILURE TO PERFORM
Overview
1) Effect of failure to perform
2) Options to rescind
3) Rights to damages
FAILURE TO PERFORM
Effect of failure to perform
Linggi Plantations Ltd v Jagatheesan:
FAILURE TO PERFORM
Options to rescind
Loke Yuen Cheng & Anor v Vintex Sdn Bhd:
1) Option 1:
2) Option:
FAILURE TO PERFORM
Rights to damages
Muralidhar Chatterjee v International Film Company Ltd:
TIME IS NOT OF THE ESSENCE
Overview
1) The law
2) When
2) Right to rescind
3) Notice to make time is of the essence
4) Relief for SP
TIME IS NOT OF THE ESSENCE
The law
S.56(2)
TIME IS NOT OF THE ESSENCE
When
KL Landmark Sdn Bhd v Standard Chartered Bank:
TIME IS NOT OF THE ESSENCE
Right to rescind
Ganam Rajamany v Somoo Sinniah: