A coating specification is a formal , legally enforceable document that tells the contractor (applicator) _____ __ ___ and _____ __ ___ __, but generally does not tell them _____ __ __ __.
what to do
where to do it
how to do it
A good specification will describe, at a minimum , the ____ __ ___ ___, materials needed, the _______ of the coating , the key _______ required, the ______ of the finished coating, the ______ by which the job will be _______, and the ________ requirements to ensure a good coating job.
scope of the job objectives procedures appearance standards judged inspection
The general portion of a specification should include the _____ of the work, the ____ of structure involved, the ______ of other structures in the areas, and the _____ of protection.
location
type
location
degree
The preparation of a specification should involve at least three of four entities.
owner
engineer/design co.
manufacture
contractor
specifying engineer is defined as the person who can resolve ____________ or make _________ to a specification
non conformance
changes
the “scope” section of a specification describes the _____ to be done, ______ and _____ it will be done, and _____ the contractor is to supply.
work
when
where
what
Any requirements for special permits, such as ______ _____, _____-____ and ___-____ procedures, ______ signals, _____ havens, ____ procedures, etc., should be included in the safety section of a specification.
confined spaces tag-out lock-out warning safe exit
Preinspection is a procedure for inspecting, ____, and ______ of all fabrication defects and/or process damages to the structure being prepared.
marking
correction
Two items that should be covered in the surface preparation of a specification are:
A recommended source for selection of coating materials is the SSPC table _________ systems for ___________ zones, which lists various environmental zones of usage and recommends corresponding __________ coatings.
painting
environmental
generic
The coating schedule should include _____ to be coated, ____ , __ ______ .
areas
protected
not coated
The work methods part of a specification should define what is meant by “good working methods” by citing the requirements of such sources as SSPC-PA 1, or requires painters to be qualified according to ASTM standards _______ and ______.
SSPC-PA 1
D4427 and 4228
SSPC
(steel structures painting council)
A good specification will state the required ____ and _____ DFT of each coat in a system as well as the ________DFT of the system, along with requirements for _____ coating of _____, ______, ____, ______, etc.
minimum
maximum
allowable
stripe coating of welds, edges, nuts, bolts, etc.
It is generally recommended that coatings not be applied where the ambient _________ is within ____ or _____ of the dew point and rising.
temperature
3 deg C or 5 deg F
dew point
A specific restriction against ________ or ________ a material as a means of _________ the pot life should be included in the specification.
Thinning or cooling
extending
The manufactures ________ instruction should be made part of the specification.
application
Depending on the number of coats , there should be a requirement for a _______ ______ __ color with the _______ coat.
sufficient contrast in color
previous
The work schedule normally includes such points as:
Inspection should be an in-process function that requires ____ _____ observation of all _______, _______ ________, ______, _________, and ______ of a coating system.
Full time cleaning surface preparation mixing application curing
The documentation section of a specification should list all the reports that are _________, the _________ of the reports, and __ ____ they should be forwarded to.
required
frequency
to whom
name the individual sections of the sample offshore specification shown in appendix 17A
“shall” and “shall not”
mean the provision is mandatory, and the contractor must comply
“should”
is not obligatory but indicates a strong recommendation to the contractor to fulfill that part of the specification.