What is the purpose of cladding or lagging any object
Protect the insulation beneath it
What 4 methods are used for material protection ?
Weatherproofing
Fireproofing
Chemical resistance
Soundproofing
What is the most common cladding material ?
Aluminum
What material is the best option when the insulation has a chance of being subjected to fires or chemical attack
Stainless steel
What are the disadvantages of stainless steel ?
Expensive
Difficult to cut and form
What material is not commonly used in cladding and lagging ?
Galvanized iron
What is the purposes of moisture barriers ?
To Prevent chemical attack at the metal insulation interface
what cladding material has an inside rubber liner added to lower sound levels ?
Muffle jacket
What size range do pressed elbows fit on ?
1”-36” inside pipe size
Who chooses the various material finishes found on cladding materials?
Design engineer
What is the most common finish used in cladding and lagging but is highly susceptible to scratching and denting ?
Smooth finish
What is the strongest and most dent/scratch resistant finish used in cladding and lagging ?
Corrolon finish
What do you use when you cut off insulation perpendicular to the length of the pipe ?
Metal end caps
What are two main types of end caps ?
Crimp type
Lock form type
When insulation is cut back at a 45 degree angle what must be used to cover the ends?
Metal bevels
What are expansion springs used for ?
Stainless steel springs used to accommodate the expansion and contraction of large diameter pipes, tanks, vessels, heat exchangers and equiptment
What are the two types of banding clips?
Wing seal type or crimp type
All laps on material must be a minimum of _____”when cladding piping and a minimum of_______” when cladding equiptment
2 “
3”
When cladding horizontal piping the laps should be placed at 2 o clock on the concealed side of the pipe with all laps placed away from prevailing winds T or F
True
What type of clips should be used when installing vertical piping ?
S clips
What may be added to a large lock formed end cap for extra strength ?
Cross break
how much overlap should accompany all overlapping vertical sheeting ?
3”
When you are installing corrugated sheeting on horizontal applications you must maintain a minimum of ________ overlap between sheets
2 corrugation
All banding clips should be placed on _______ side of the pipe when possible ?
Concealed side