What are the Seven aspects of a Vertical Cost Breakdown?
IBID-CM-E
List 2 methods of pricing out direct cost estimates
Define Swing Shift
the work shift between the day and the night shifts, commonly from 4:00 PM to midnight
3 Types of Estimate for an Owner
3 Types of estimate for a contractor
Two different breakdowns of cost:
Horizontal and Vertical
Horizontal: 7 Categories
PEE-RSLL
Vertical: 7 Categories
IBIDCM-E
List 3 types of mark-up
Home office, Profit, and Risk
List The 4 Types of EOE
Equipment Operating Expense
List the 5 Types of Indirect Costs
Contingency
Safety net accounting for risks
2 Types of Contingency
Identified & Unidentified
3 Categories of Unidentified Contingency
What is an unidentified contingency?
A little bit of padding thrown into your estimate for small, unanticipated events.
List the 2 categories of risk.
Quantifiable & Unquantifiable risk
2 Types of Network Diagrams
AoA - Activity on Arrow
AoN - Activity on Node
What is a schedule?
A schedule is a logical representation of logical relationships / sequences of tasks or activities.
IPA
Immediately Preceding Activity
Dummy Relationship
Logical relationship with no time associated
(CP) Critical Path
The longest path through the network.
Activities with zero float are considered critical path tasks.
Critical Activity
Any activity on the critical path
Float
The difference between the available time to complete an activity and the required time.
a. non-critical activities have float
b. critical activities have no float
4 Types of Logical Relationships
Start-Start
Start-Finish
Finish-Finish
Finish-Start
The default is Finish-Start relationship