Summarise your work in Cost Audits of Sub-contractors?
I ensured that the client was made aware of all outstanding issues with the Sub-contractors payment methodology and what the sub-contractor agreed to change as a result. For example the sign-off process was inadequate without sufficient controls.
Summarize a time you acted ethically?
At NNEP.
Contractor submitted wrong rates.
Advised that these should be reduced to match agreed rates.
They agreed and reduced the amount submitted in the AfP.
Cost Estimating and planning, how did you provide value-for-money for the client?
Example of construction tech knowledge in practice?
Example of contract practice, SALUS AfP?
Example of when you advised the Client to shut down the contract?
Example of when you worked on Option C contract?
I calculated Pain/gain shares on 13 Option C contracts.
Tell me about how you shut down the contract at NNEP?
Underperforming on older framework contracts, and shut down the historic framework to move works onto new compliant framework.
Forecasting was not being updated, despite being in the contract.
Were weren’t the RAG options given weightings?
It was clear from the initial RAG that Option 1 performed the best, even if given weightings as it was the best performer in the key objectives and throughout.
What were the luminaire requirements at Heathrow?
British Lighting Standards apply.
Process control room 300 lux. Walkway/corridor 50 lux.
What incentive packages are applied to Heathrow Option E contracts?
X clauses.
X5 sectional completion.
X7 delay damages.
In terms of quotation timescales, how did you change this?
The contractor needed more time in order to produce a particularly complex quotation, so discussions were held to allow the contractor more time under the contract for that particular CE.
Example of underperformance of a contractor?
Contractor was unable to provide adequate resources to complete one of the projects due to other projects at the same time ongoing.
Example of when you negotiated with a contractor?
Negotiated how to allow for scope that was needed but they had not received any quotations for. It was understood that a value needed to be included, but provisional allowances weren’t allowed under NEC. I negotiated to ensure that the contractor provided quotations from a supplier to back up the figures before the gateway governance.
What procurement regulations does Heathrow use?
Competition Law, not PCR
Competition Act 1998
What is the role of the RICS?
Advance knowledge, uphold standards, and inspire professionals.
How does the RICS operate?
The RICS operates with a set governance structure, with the Privy Council sitting above the RICS governing council, which sits above the SRB and the RICS management board.
What are the requirements of RICS royal charter?
Promote the usefulness of the profession, uphold standards, and act in the public interest in the UK and globally.
What is a certificate of insurance, and why is it important?
It certifies that a firm holds insurance and the details of that insurance.
What is informed consent?
Informed consent is where there is a conflict of interest identified to the client, but the client wishes to proceed anyway.
What are some examples of data barriers?
Sharepoint, document passwords, physical barriers between departments in offices.
How do you ensure public confidence is maintained through your work?
Ensuring that all work is value-for-money.
How do you encourage D&I through your work?
Running a social value charter with National Highways.
Always ensuring to do a D&I moment before meetings.
How did you advise on Ethics?
I completed cost assurance of subcontractors at Network Rail, Thames Water and Thames Tideway.
While at NNEP, I advised the client that the contractor was using greater rates than allowed under the framework agreed rates, and advised the contractor to reduce these rates. This is ethical to ensure that public money used on this project is value-for-money.