What are the stages of design from inception to completion
RIBA Stages (2020):
0 - Strategic definition.
1 - Preparation and briefing.
2 - Concept design.
3 – Spatial Coordination
4 - Technical design.
5 – Manufacturing and Construction.
6 - Handover.
7 - use.
explain the RIBA stage 0:
RIBA Stage 0 – Strategic Definition
Core Tasks:
Designers contribute to client requirements (limited involvement to no involvement)
Sustainability – strategic plan in relation to client requirements (developing existing buildings or extending as opposed to demolition or maybe a new structure is not required)
explain the RIBA stage 1:
RIBA Stage 1-Preparation of Brief
Stage Outputs:
explain the RIBA stage 2:
RIBA Stage 2 – Concept Design
Stage 2 Outputs/Deliverable:
-Develop basis of design (i.e. define structural standards, loadings, fire resistance, serviceability criteria, etc) – technical interpretation of project brief.
Identify whether specialist subcontracts are required in basis of design.
-Develop a foundation strategy.
-Deliverables list (define what needs to be delivered at each stage).
-Design programme to be developed by lead designer and agreed with client and all other designers.
-Structural sustainability report (can be included in basis of design – how will sustainability targets be achieved).
-Initial structural drawings (i.e. sketches of grids, no BIM required by engineers). However, this needs to be confirmed by the project team and client if 2D or 3D models are required.
-There is a risk on progressing too much with a detailed 3D structural model due to later changes at stage 3 of RIBA stages 2020.
explain the RIBA stage 3:
RIBA Stage 3 – Spatial Coordination
-Concept design should be progressed and not changing at this stage for single solution that aligns with project brief.
-Further design studies for a preferred option.
More details – detailed structural model and calculations for design solution and cost exercises.
Design solution for economy of materials through detailed analysis.
-Confirm structural grids and zones.
-Spatially co-ordinate structural design and integrate with other disciplines (MEP zones locations need to be identified).
-GA’s should be signed off in this stage to allow progression into stage 4 of RIBA stages 2020.
Consider construct-ability issues at this stage (Can the structure be built through conventional means or is it a complex process)?
-Risk should be highlighted at every stage of the RIBA plan of works but specific temporary works items need to be identified and communicated to the contractor (i.e. jacking/preloading/temporary supports or undermining)
-Assist lead designer with preparation of design programme.
Stage 3 Outputs/Deliverables:
explain the RIBA stage 4:
RIBA Stage 4 – Technical Design
Stage 4 Outputs/Deliverables:
explain the RIBA stage 5:
RIBA Stage 5 – Manufacturing and Construction
-Construction on Site has begun and at this stage, we should be involved in solving site queries (who is responsible?).
-Undertake site visits and inspections.
-Prepare Building Log Book, O&M Manual
-There is typically an overlap between stage 4 and 5 in RIBA stages 2020.
‘-As-constructed’ information to be prepared and agreed by relevant parties
-Stage ends with practical completion of the project.
Stage Outputs:
explain the RIBA stage 6:
RIBA Stage 6 - Handover
-Building is officially handed over, Aftercare initiated and Building contract concluded.
-Construction team rectifies any residual defects.
Project performance needs to be facilitated (Lesson learned)
-Post occupancy evaluation.
-Has sustainability targets been achieved ? (needs to be documented and refer to RIBA stages 2020)
explain the RIBA stage 7:
RIBA Stage 7 - Use
Can you tell me some of the legislation that impacts on the design operation and maintenance of buildings?
Town and country Planning Act
Construction (Design and Management) Regulations 2015
Control of Substances Hazardous to Health Regulations (COSHH) 2002
Health and Safety (Consultation with Employees) Regulations 1996
Health and Safety at Work etc Act 1974
Lifting Operations and Lifting Equipment Regulations (LOLER) 1998
Management of Health and Safety at Work Regulations 1999
Provision and Use of Work Equipment Regulations (PUWER) 1998
Work at Height Regulations 2005
What do we mean by operational and maintenance process of a building post contract?
Building operations consists of the activities necessary to operate, maintain, and manage buildings. This includes maintaining the HVAC systems, plumbing, electrical, and building system configuration.
Maintenance Techniques - Maintenance strategy and control, transitioning from reactive to proactive maintenance, maintenance contracts, establishing a minimum standard for inspection and maintenance of equipment, operating and maintenance documentation, and maintenance technician training.
Owning and Operating Costs - First costs of building ownership, new building construction project delivery methods, estimating costs, service life, depreciation, recurring cost, maintenance costs, utility costs, regulatory costs, utility billing analysis, and economic analysis
Heating, Ventilating, and Air-Conditioning Controls - Control components, specifying control systems and writing control sequences, effective use of control technology, using the control system for energy management, impact of controls of operating costs, emerging control technologies and strategies.
Risk Assessment Procedures - Defining risk, emergency response plans, activating an emergency response plan, types of risk and what to do during an emergency, and what to do after an emergency.
Greening Your Facility - Utilizing a building monitoring system to understand the energy costs related to each piece of equipment in real time. In addition, tenant submetering helps ensure that tenants are incentivized to reduce costs.
Health and Safety - Health and safety regulations and policies, organizational health and safety programs, safe work practices, and building operating regulations.
Contractor Start-Up and Handover Procedures - Pre-start-up procedures, equipment and system start-up and testing, operator training, substantial completion and occupancy permit, handover procedures, record drawings, operating and maintenance documents, warranty, and post warranty operation.
Commissioning and Testing - Commissioning process and benefits; functional acceptance testing; testing, adjusting, and balancing (TAB); and existing building commissioning
Can you name some modern construction techniques?
Cross Laminated Timber
Timber Frame
Modular Construction - SIPS panelled
Volumetric Construction - factory built
What are the basic elements of a building?