Construction technology Flashcards

(48 cards)

1
Q

What is the build up of a flat cold roof?

A

Plasterboard, vapour control layer, roof structure, insulation in between, deck, covering. [Part H].

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How did you prevent potential problems from a cold roof?

A

Ensure there’s enough ventilation throughout the roof.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

a) Where would you expect to see a cavity barrier?
b) Why?

A

a) Between walls, floor and around windows and doors [wall cavity].
b) Prevents the spread of fire and smoke to other areas and floors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What would you need to consider when constructing a partition wall?

A
  • AD B: Need to be fire rated i.e. a protected corridor? [12.5mm plasterboard, fire doors].
  • AD M: min 1.2m wide.
  • Installing deflection heads.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a deflection head?

A

A detail at the top of partitions to allow for structural movement of the floor/roof above.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What type of sand is required for lime mortar?

A

Washed sharp sand.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What’s the difference between hydraulic and non-hydraulic?

A

Hydraulic is stronger, non-hydraulic is more flexible.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When was cement mortar first used?

A

Around the 1800s.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What causes spalling brickwork?

A
  • Freeze-thaw.
  • Water ingress.
  • Putting cement mortar on lime mortar (water escapes through brick face).
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

You mention artificial slates, how do you recognise them?

A

They have straighter and more complete finish compared to natural slates which are rougher.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the limitations of a VRF system?

A

You can get leaks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Note: Con Tech - 18-20 Tileyard Road.
- TDD.
- Water staining.
- Gap between asphalt and bitumen felt capping.
- Redress upstand detail to include lead apron or install flashband.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

a) What is an Initial Notice?
b) What’s the alternative to using an Inital Notice for Building Regulations?

A

a) Notify local authority that construction has started and BCA is being used.
[Local authority has 5 working days to review and reject otherwise it passes]
b) Full Plans Application [LABC route].
[Initial Notice is for BCA route].

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Note: Con Tech - Beckton Gateway Retail Park:
- TDD (pre-acq).
- Captured construction forms and building fabric.
- Recommended investigating insulation spec within insulated render [fire safety].
[- Euroclass B required (insulated render met this)]

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Beckton Gateway Retail Park: Where would you find the specification of the insulated render?

A
  • O&Ms.
  • Manufacturer.
  • Client.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Timber Mill Way: What did you report to the client?

A
  • Missing intumescent strips and smoke seals.
  • Gaps in doors too big [10mm].
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Timber Mill Way: What did you recommend as remedial works?

A
  • Retrofit strips and sealant.
  • Ease and adjust doors to reduce gaps to appropriate levels.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Timber Mill Way: What are the required gap measurements?

A

Gaps:
- Top and sides: <4mm.
- Bottom: <8mm [where there’s no threshold seal] or <3mm [if smoke seal required].

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Timber Mill Way: Are you qualified to recommend remedial works/specifiy fire door works?

A
  • I can specifiy works/remediation.
  • Sign off must be done by BCA if a new door [certified installer provide certificates demonstrating proper installation which a BCA can use as evidence i.e. BM TRADA, Certifire]
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

18-20 Tileyard Road: What levels should the covering, apron and capping [lengths] be?

A
  • Upstand [asphalt]: min 150mm above roof level.
  • Apron [lead]: min 75mm over covering.
  • Lead laid in max 1.2m lengths [to allow for movement].
21
Q

18-20 Tileyard Road: What repairs did you recommend?

A
  • Upstand [asphalt]: min 150mm above roof level.
  • Apron [lead]: min 75mm over covering.
  • Replace old bitumen felt capping with new.
22
Q

18-20 Tileyard Road: What guidance did you refer to for the repair?

A

BS 6229 [gives measurements i.e. 150mm upstand and 75mm apron].

23
Q

18-20 Tileyard Road: What did you consider when advising the client?

A
  • Cost [asphalt upstand and lead apron vs flashband].
  • Lifespan of remediation.
    [- Measurements [150mm, 75mm].]
24
Q

18-20 Tileyard Road: What can cause cracking of asphalt and bitumen felt?

A
  • No movement joints.
  • Freeze-thaw.
  • UV degradation.
  • Age.
25
18-20 Tileyard Road: a) What grade was the lead apron? b) Why did you specify this?
a) Grade 4 (1.8mm). b) Followed BS 12588 which stated that this was the appropriate code of lead for this application.
26
18-20 Tileyard Road: What flat roof tests did you undertake aside from visual inspections?
- Damp meter on timber structure (normal reading - no rot). - Core sampling [didn't do this but is an option]. [18-20% indicates moisture is present could lead to issues, over 20% considered high].
27
Timber Mill Way: What regulations or guidance did you refer to when advising the client?
- AD B [regulations to comply with]. - BS 8214 [how to install and maintain to comply with regs].
28
Timber Mill Way: What is an 'S' fire door?
Prevents smoke as well as fire. [FD30S - prevents fire and smoke] [FD30 - prevents fire only]
29
Timber Mill Way: a) Did the door have any kitemarks? b) How else did you know it was a fire door?
a) Yes. b) Door was 45mm thick [FD30].
30
Timber Mill Way: a) Did you need building regs approval following the installation of intumescent strips and smoke seals? b) What if the door wasn't a fire door originally and you retrofitted the strips and seals?
a) No, as it's repair/maintenance (door already a fire door) [kitemarks, 45mm thick - standard doors are 35mm]. b) Replacement of the fire doorset would be needed [doorsets need to be certified as they're tested - standard doors aren't].
31
Beckton Gateway Retail Park: a) What was the Euroclass rating of the insulated render? b) What did it need to be?
a) Euroclass B. b) minimum Euroclass B.
32
Beckton Gateway Retail Park: You mention checking the insulated render specification to ensure it complies with relevant standards. What are these standards?
- AD B [external walls must limit spread of fire]. - Euroclass rating [B rating required as stated in AD B].
33
Beckton Gateway Retail Park: Can you talk me through the buildup of the building envelope?
- Steel portal frame. - Built up cladding to roof and elevations. - Brickwork and insulated render to standalone structures.
34
Beckton Gateway Retail Park: Who did you recommend to undertake further investigation?
Said I would do it but needed O&M information from the client.
35
Beckton Gateway Retail Park: What statutory documents did you review?
None, not available before inspection.
36
CBXII: What are the key requirements under AD K regarding safety glazing, and how did these influence your recommendations?
Glazing below 1500mm from floor level needs safety glazing [glazing adjacent to a door - within 300mm]. [800mm rule is for windows]
37
CBXII: What factors did you consider when advising the client on retrofitting safety film versus full glazing replacement?
- Condition of glazing. - Cost. - Short-term [10-15 years].
38
CBXII: What are the characteristics safety glazing offers?
- Less risk of injury if it breaks. - Cost [cheap]. - Time [quick to install].
39
CBXII: What are the benefits and drawbacks of safety film versus replacement?
Safety film: - Cost [cheaper]. - Time [quick]. - Short-term [maintenance]. Replacement: - Better performance. - Long-term. - Expensive.
40
CBXII: Why are kitemarks important?
Provides evidence glazing meets building regs [AD K].
41
CBXII: What issue did you identify with the glazing during the survey?
- Glazing below 1500mm limit. - Didn't comply with building regs [AD K]. [- No kitemarks.]
42
CBXII: What are the limitations of retrofitting safety film from a compliance and durability perspective?
- 10-15 years [safety glazing 30+ years]. - Peel or scratch [replacement may be required]. - No fire resistance.
43
CBXII: What does AD K say about retrofitting safety film?
- Details performance criteria. - Break safely [glass should]. [- Resist impact without breaking] [- Be protected from impact (something prevents occupants striking the glass)]
44
18-20 Tileyard Road: a) How would you assess the remaining service life of the asphalt flat roof? b) How did this affect your advice?
a) - Visual inspection. - Cracking and blistering to surface. b) - Wasn't deteriorated enough, so repairs tonupstand only. - Would propose full replacement in addition to upstand repairs if at the end of it servicable life.
45
Timber Mill Way: What is a nominal and notional fire door?
Nominal: - Typically fire resistant but not certified [i.e. solid timber]. - Can be upgraded to comply [strips and seals, good fit etc]. Notional: - Typically not fire resistant. - Needs replacing.
46
Timber Mill Way: a) Can regular contractors remediate fire doors? b) Would Building Regulations approval be required following completion of the repairs?
- AD B states competent contractor only required not third-party approved installer. - No, strips and seals installation considered an upgrade not material alteration.
47
Timber Mill Way: How would the fire doors be adjusted to close the gaps?
- Adjust hinges. - Use packers behind hinges.
48
18-20 Tileyard Road: a) What would you expect to be present at the bottom of the junction? b) What would you recommend be installed here to account for thermal movement between the asphalt and enclosing wall?
a) Concave fillet. b) Slip sheet.