How did you apply constrution technology knowledge (UHL Small Ward CT)
What impact did the lead sheilding have on costs (UHL Small Ward CT)
Significantly more expensive (circa £150 plus per m2)
Room - 35m2 (5.5m x 6.5m)
Walls - 75m2 (24m x 3m)
Cost - £25k uplift from £13k
Other materials that were considered (UHL Small Ward CT)
Concrete was considered, it is:
- Thicker
- Cheaper
- Slower construction
Why were bored piles chosen instead of driven piles
Extension within hospital estate
Vibration and noise needed to be minimused to avoid disturbing patients and medical equipments
How did the modular build affect technical considerations
Mod units require precise and reliable foundation solutions to ensure accurate placement and alignment