What is the role of a Contract Administrator?
What are the main responsibilities of the CA?
-Administer the Contract
- Chair meetings
-Report to the client
- Issue certificates under the contract (e.g Extention of time, PC, Non completion)
- Authorise payment
- Give contract instructions
-
What is a Letters of Intent?
A letter of intent is a method of instructing a contractor to proceed with the works before formal execution of the contract.
Why might a LOT be used?
What would be included in an LOI
What is a pro and con of using a LOI?
Pros - It creates a moral commitment to parties involved and alleviates programme constraints
Cons- Can be a complicated legal situation and can be a risk to both parties
What would you include within tender documents?
What are the main certificates under JCT Forms of Contract?
What are the main certificates under JCT Forms of Contract?
What are the main forms of Contract in the JCT Suite?
What are dispute resolutions available under the JCT Suite of Contract?
- Arbitration (Legally binding)
What are the differences between JCT Minor Works and Intermediate?
Express provisions for:
What procedure take place one the rectification period ends?
When would you issue PC and what happens one issued?
Why would you use a JCT minor works contract?
What are the payment procedures under JCT Contracts?
What is a Variation?
An alteration to the scope of works in a construction contract. It can be in the form of an addition of omission.
How would you agree the value of a variation?
What provision within a JCT Contract could be used to resolve a dispute regarding valuing a variation?
Under 3.6.2 the CA can set the value of work should no agreement be possible. The contractor can’t refuse to comply with an instruction simply because a price hasn’t been agreed.
What are LADS?
Liquid Ascertained Damages are a genuine pre-estimate of loss incurred by the employer should the contacted completion date not be met.
What might the value of LADS be based on?
What must occur before LADs can be claimed by the employer?
Under JCT Contracts the CA must issue a certificate of non completion as a pre- requisite of claiming LADS
What is an Extension of time?
It can be granted to the contractor, where the completion date is adjusted, relieving them of LADs for extention period.
How would assess an extension of time request?