What is the role of a Contract Administrator?
To administer the contract between the employer and the contractor.
CA to act independantly, impartially and fair when making decisions.
When does the contract admin role begin?
The role of contract administrator does not commence until a building contract is in place between the employer and the contractor.
However, there is often arrangements in place between the client and CA to undertake pre-contract duties such as:
- Selection of the method of procurement.
- Deciding on the type of building contract.
What are the responsibilities of a Contract Administrator?
Administer the contract between the employer and the contractor.
The CA must act in a manner which is independent, impartial and fair when making decisions.
Completing multiple other administrative tasks such as:
- Managing changes to the contract such as variations.
- Undertaking routine inspections to inspect quality, progress and valuations.
- Issuing payment certificates /practical completion certificates.
Who can act as Contract Administrator?
Traditionally, the role was undertaken by an architect; the role can also be undertaken by:
- Building surveyors
- Quantity surveyors
- Management surveyors
- Engineers
You have said that you’ve read the RICS Contract Administration Guidance Note – can you tell me a bit about that?
What are the key points of the RICS Contract Administration guidance note?
Is the RICS Contract Administration guidance note mandatory?
No, this is a guidance note and therefore considered best practice.
What are the different types of contracts you are aware of?
My experience with contract administration has been from administering the JCT suite of contracts. These are:
- Minor Works (+ with contractors design)
- Intermediate Building Contract (+ with contractors design)
- Standard Building Contract
- Design & Build
- Repair and Maintenance Contract
What do you consider when selecting which contract to use?
Are you aware of any other forms of contract? (other than JCT)
I am aware of the NEC contract suite but have not had any experience in administrating this.
What is the difference between JCT and NEC?
What are the different types of procurement methods you are aware of?
Explain to me your understanding of Management Procurement?
Advantages:
- Quick method of procuring a main contractor.
- Programme and cost plan agreed by design team.
Disadvantages:
- Method requires high level of client involvement.
Explain to me your understanding of Design & Build?
Advantages:
- Time can be saved by starting the construction works whilst the design is completed.
- Design & construction risks lie with the contractor.
Disadvantages:
- Contractor assumes higher risk and this is reflected in the price.
Explain to me your understanding of Traditional Procurement?
Traditional procurement involves separating design from construction.
Advantages:
- Control of quality.
- Client knows lump sum cost.
- There is a contractual date for completion.
Disadvantages:
- Design risks lie with the client.
- Long design period.
What should you consider when advising on a procurement route?
Whats the difference between single stage and two-stage tendering?
Traditionally, tendering involves just one stage, in which a contractor is appointed to carry out all of the works required.
In Two-stage tendering, the contractor is initially appointed only to carry out some of the works required. Allows early appointment of a contractor whilst designs are being finalised for a second stage.
What’s the difference between patent & latent defect?
Patent defects
- Defects that can be discovered by reasonable inspection.
Latent defects
- Defects that cannot be discovered by reasonable inspection.
For example, problems with foundations which may not become apparent for several years after completion when settlement causes cracking in the building.
Time barred 6 /12 years depending how contract is executed,
What is a tendering process?
Why is tendering important?
Tendering helps all parties arrive at the best contractual terms that benefit all parties.
Whats is a Provisional sum?
Allowance for work that has not been described in enough detail at the time of tender to be accurately priced.
Two forms of provisional sum:
Defined
- Described in sufficient detail for the contractor to provide time and cost (confirming floor colours)
Undefined
- Works are not described in sufficient detail for the contractor to provide time and cost (drainage repairs following CCTV survey).
What is a Prime Cost Sum?
A cost that has been obtained prior to requesting tenders usually from a sub contractor /specialist.
The main contractor is entitled to add mark up and attendance costs to the allowance.
What are the insurance options in JCT?
Option A: Contractor all risk.
- The responsibility of the Contractor to arrange insurance for the entire project.
- Takes out joint names for all risks insurance of the works.
Option B: Employers insurance of works.
- The client takes on the responsibility of arranging insurance for the works.
- Provides employer with greater control /assurance over the insurance.
Option C: Joint names insurance.
- Contractor and the client named as joint insured parties.
- Simplifies claims handling.
How would you select the insurance option for a contract?
The choice between Options A, B & C depends on the project requirements, risk and the parties ability to secure appropriate insurance cover.
I ask the client to run this by there insurers.