How does the role of a CA differ from that of an EA?
The CA administers the contract, while the EA is responsible for all duties the employer would usually perform.
The CA is impartial.
What happens at practical completion regarding retention?
50% retention is released and the 12 months defects period starts.
The ability to impose Liquidated Damages ceases.
What is a performance bond?
A performance bond is issued as a guarantee against the failure of one party to meet obligations in the contract.
When may a performance bond be required?
What types of performance bond are there?
What is time at large?
There is no current fixed date for completing works.
What is loss and expense in contract terms?
Contractor can claim loss and expense due to Employers’ error.
What are relevant matters in contract claims?
They entitle the contractor to claim loss and expense.
Examples include variations, instructions, and impediment by the Employer.
What is a Relevant Event?
Entitles the Contractor to an Extension of Time (EoT).
What are some examples of Relevant Events?
What is force majeure?
Act of God.
If there are concurrent delays, is there an entitlement?
There are no clear rules; each case must be judged separately.
How is the construction Act relevant?
It contains statutory provisions relating to all projects over 45 days.
What is the purpose of retention?
An amount deducted from payment to the contractor, retained until practical completion and end of Making Good Defects (EoMGD).
What is an alternative to retention?
Retention bond, provided by the contractor for the same value.
What happens when practical completion (PC) is granted?
What happens at the end of the rectification period?
A statement is issued for any defects, and a Certificate of Making Good is issued, triggering final valuation and release of retention.
What does the final certificate represent?
Agreement that all contractor works are complete, contract sum is agreed, and any EOTs and L&E has been closed out.
What’s the difference between termination and suspension?
Termination is lawful stopping of contract works; suspension is where the contractor stops works.
What are the advantages of using a JCT Design & Build (D&B)?
What are the disadvantages of using a JCT D&B?
What is the vesting process?
Pre-contract, a vesting certificate is drawn up, signed by both parties, and materials are itemized and documented post-contract signing.
How can payment be made under the rugby utilities work?
What is the form of contract used on the rugby utilities work?
JCT MW 2016 with milestone-based payment terms.