Contract Admin Flashcards

(88 cards)

1
Q

What are the key differences between JCT Minor Works and JCT Intermediate?

A

JCT Minor Works (MW):

  • Simple, low-risk projects.
  • Limited M&E & specialist works.
  • Client retains most design responsibility.
  • Minimal procedures & contractual administration,

JCT Intermediate (IC):

  • Medium complexity projects, mulit-trades.
  • More detailed specifications, more complex M&E.
  • Emphasis on coordination and contractor obligations.
  • More robust clauses for design portions, programming and variations.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What documents make up a JCT contract package?

7

A
  • Contract Conditions
  • Prelims & programme
  • Pricing documents / tender returns
  • Employer’s Requirements / Specifications
  • Schedule of Amendments (SOA)
  • Drawings
  • Clarification documents
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the primary duty of the Contract Administrator?

A
  • Manage the contract for the client.
  • Monitor progress, approve payments, and handle variations.
  • Act as the main communication point between client and contractor.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Name key CA responsibilities under JCT.

7 points

A
  • Issue instructions (CI)
  • Certify interim payments
  • Certify EOTs
  • Certify Practical Completion and Final Certificate
  • Assess delays/claims: Evaluate extensions of time and related claims.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a variation under JCT Minor Works?

5 points

A
  • Change to the original work, materials, or specs.
  • Issued by the Contract Administrator.
  • May affect cost and completion time.
  • Formally recorded to avoid disputes.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How does a CA issue a valid Contract Instruction?

A
  • Written and clear: Specify the work required.
  • Refer to contract clauses (e.g., JCT).
  • State cost/time impact if any.
  • Officially issued to the contractor.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How are variations valued?

6 points

A
  • Use contract rates if available.
  • Contractor quote for new or omitted work.
  • Daywork based on labor, materials, and plant.
  • Agree cost with contractor before proceeding.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a Relevant Event under JCT?

A

Events potentially entitling the contractor to a EOT listed in the contract , such as:
* Variations
* Delay by CA/client
* Statutory undertaker delays
* Force majeure
* Exceptionally adverse weather
* Time relief only - Not automatically loss and expense

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What must the contractor do to claim an EOT?

A
  • Notify the CA as soon as reasonably practicable
  • Provide details of cause, delay impact, and evidence
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the CA’s duty when assessing EOTs?

A
  • Act impartially
  • Make a fair and reasonable assessment
  • Issue decision before completion date
  • Adjust Liquidated Damages accordingly
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a Relevant Matter?

A

An event entitling the contractor to recover additional cost, e.g.:
* Variations
* Failure to give possession
* Delay caused by CA/client
* Disruption
(Differs from Relevant Events which affect time)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is Loss & Expense in a JCT contract?

4 points

A
  • Compensation for extra costs or delays beyond the contractor’s control.
  • Covers direct costs (labour, plant, materials) and indirect costs (overheads, prolongation, lost profit)
  • Must be recorded and agreed by the CA
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What evidence is needed for a Loss & Expense claim?

6 points

A
  • Costs breakdown
  • Prelims build-up
  • Overheads & plant records
  • Invocies/Receipts
  • Justification
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How is Loss & Expense assessed?

5 points - direct, indirect

A
  • Direct costs- Labour, plant, materials
  • Indirect - prolongation cots, overheads, loss of profit
  • Assessed by CA
  • Must be evidenced, attributable and reasonable
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are CA responsibilities during interim valuations?

6 points

A
  • Assess and value work to date
  • Include variations
  • Issue Payment Notice & certificate
  • Ensure compliance with Construction Act 1996
  • Confirm Retention deductions if applicable
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the statutory payment requirements?

A
  • Prompt interim payments for work done.
  • Payment notices confirm amounts due.
  • Pay less notices explain deductions.
  • Final payment on completion.
  • Adjudication: can be triggered anytime a payment dispute arises
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

How is Practical Completion defined?

4 points

A
  • Works are complete, fit for occupation
  • No material defects remain
  • Only minor snagging tolerated
  • Building compliant with statutory requirements
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What does a tender analysis involve?

7 points

A
  • Compare prices and scope.
  • Assess contractor capability and experience.
  • Evaluate risks and consistency.
  • Recommend the most suitable contractor.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Why are formal notices important?

4 points

A
  • Protect contractual rights
  • Avoid disputes
  • Maintain audit trail
  • Ensure compliance with time limits
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is the difference between formal and informal communication?

2 points

A
  • Formal: Contractual notices with legal effect
  • Informal: Emails, discussion notes, minutes (supportive evidence only)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is the difference between a simple contract and a deed?

4 points each

A

Simple Contract
* Can be oral or written
* Limitation period: 6 years
* Common for standard construction contrac6s

Deed
* Must be written, signed, witnessed, and delivered as a deed
* Limitation period: 12 years
* Used for formal agreements, warranties or higher risk projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is the difference between an express term and an implied term?

A

Express Term
* A term explicitly stated in the contract
* Usually written or verbally agreed

Implied Term
* A term not written down, but implied by law etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

How do you ensure impartiality when acting as Contract Administrator while being employed by the client?

6 points

A
  • Follow contract terms.
  • Document all decisions clearly.
  • Be transparent with client and contractor.
  • Avoid conflicts of interest.
  • Refer to professional guidance if needed.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What are the changes to JCT?

2016 and 6 points

A
  • JCT 2016 no longer purchasable from 31 March 26

JCT 2024:
* Modernisation: gender‑neutral wording, electronic notices & e‑signatures permitted.
* New Relevant Events: epidemics, asbestos
* Design liability clarified: limited to skill and care, excludes fitness for purpose.
* Dispute and payment updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
What is the payment cycle? | 6 Points & purpose
* Application: Contractor submits interim payment * Due Date: Payment becomes due - 7 days * Last date for CA to issue Payment Cert 12 days * Payment Notice: Employer states reduced sum due within 5 days of the Due Date - 16 days * Final Date for Payment: 21 days Day 0 → Interim Valuation Day 7 → Due date - Payment becomes “due” Day 12 → Last date for CA to issue Payment Cert Day 16 → Last chance for a Pay Less Notice Day 21 → Final date for Payment
26
What is HGCRA 1996
* Housing Grants, Construction and Regeneration Act 1996, * Key piece of UK legislation governing construction contracts
27
HGCRA purpose? | 3 points
* Encourage prompt payment in construction contracts * Provide a mechanism for dispute resolution * Improve cash flow in the construction industry
28
What is a payment notice
* Formal notice stating amount due and payment date. * Ensures clarity and compliance with contract rules. * Helps prevent payment disputes. * It is a statutory requirement under the HGCRA 1996
29
What is a pay less notice?
* Employer notifies they will pay less than claimed. * States amount and reason. * Ensures compliance and clarity to avoid disputes. * Serve within contract period or ≥ 5 days before Final Date for Payment.
30
What would you do if the client wanted to pay less than the sum on the certificate? | 7 points
* Check contract/statutory rules. * Advise client on legal requirements. * Issue pay-less notice with amount and reason. * Send before payment due date. * Document all actions.
31
What happens if the contractor disputes an undervaluation? | 3 steps
* Contractor notifies CA / Employer in writing with evidence. * CA reviews and may amend the Interim Certificate, updating the notified sum. * If unresolved, dispute can go to adjudication or contractual dispute resolution.
32
Why is prompt payment important in construction and what is the purpose of HGCRA 1996?
* Maintainscash flow healthy. * Reduces disputes. * Supports project progress. HGCRA 1996 Purpose: * Guarantees statutory interim payments. * Ensures prompt payment and fair treatment. * Provides adjudication for quick dispute resolution.
33
What act brought about the current valuation process? | Act, introduced for & ensures
* Housing Grants, Construction and Regeneration Act 1996 * Ensures: cashflow + clear payment mechanism
34
What rights does the HGCRA 1996 give a contractor if the employer fails to pay? | 3 points
* Right to interim payment * Right to interest: On late payments. * Right to suspend work: If payment is not made after proper notice. * Right to adjudication
35
Why did you use a JCT MW Contract for your case study
* Project size/value: * Low complexity * Clear roles: Obligations of contractor, CA, and client defined. * Single-stage tender: Suits traditional procurement for small projects. * Time/cost certainty: Fixed sum and 7–9 week programme.
36
What is a certificate of Non-completion
* Issued by Contract Administrator when works are not complete by the completion date * Confirms areas or items of work still outstanding * Can trigger liquidated damages or extensions of time considerations * Provides formal record
37
What is the effect of PC?
* Release of half retention * Employer takes possession + insurance responsibility * Defects rectification period starts * LADs stop at PC
38
When and how do you issue a certificate of making good defects and what are the implications?
* Issued at end of defects rectification period (6–12 months post-PC) * CA inspects → confirms defects remedied → issues certificate * Contractor receives final half retention
39
What happens if the contractor does not return to make good defects?
* If contractor doesn’t return → CA can instruct others to fix defects * Employer recovers cost (set-off against retention or sums due) * No MGD issued until works rectified * Contractor still liable for defects
40
When preparing tender reports, do you always make recommendations based on cost?
* Not cost alone → based on client’s objectives * Factors: programme, quality, contractor capability, risk, compliance, sustainability/social value * Recommendation = balanced + aligned with client priorities
41
What guidance note did you refer to when tendering?
* Guidance: RICS Tendering Strategies (2010) * Selecting and managing the tendering process to achieve value for money, fairness, and transparency .
42
Can you explain the difference between single-stage and two-stage tendering? | process, use, pros and cons
* Single-stage: full design and specifications provided; contractors submit final lump-sum bids once. * Two-stage: Contractor selected first, price finalised later; used for complex or developing designs.
43
Sectional completion vs partial possession?
* SC: Pre-agreed in contract → sections with separate completion dates, LADs, retention. * PP: Agreed during project → employer takes part early (contractor may refuse). DLP + insurance start for that part. * Difference = SC = planned; PP = ad hoc
44
What are the benefits for the employer in taking partial possession? | 3 points
* Early occupation/use of facilities * Revenue generation earlier (rent, business use)
45
What are the risks for the employer in taking partial possession? | 5 points
* Insurance → employer responsible from PP * DLP → starts earlier for that part * LADs → can’t claim on possessed section * Employer assumes maintenance/H&S duties
46
If the contractor suspends works for non-payment, what happens to the completion date? | 4 points
* Contractor suspension (non-payment) → entitled to EoT * CA must adjust completion date * Contractor entitled to costs of demob/remob
47
What is the difference between suspension and termination under JCT?
* Suspension: temporary, stays in contract, resumes after remedy, EoT + costs allowed * Termination: Permanent end of contract due to serious breach or default
48
What are the termination grounds under JCT for both employer and contractor
Employer: * Contractor abandons or delays work * Persistent non-compliance * Insolvency or bankruptcy Contractor: * Employer fails to pay * Blocks access or withholds info * Prolonged suspension/delay
49
What are the consequences of wrongful termination? | 4 points
* Wrongful termination = contract breach * Innocent party may claim damages * Terminating party may be liable for damages costs * Causes reputational damage.
50
What alternatives might you advise a client before terminating a contractor? | 6 points
* Issue notices to remedy breaches or delays. * Negotiate extensions or revised programme. * Mediation or dispute resolution to settle issues.
51
What is the post-termination process for the Employer under JCT? | 5 points
* Employer secures site, plant, materials, part works * Contractor paid for work properly done to termination date * Employer appoints new contractor to complete works * Employer can recover extra costs if contractor defaulted
52
Which document takes priority if there’s a discrepancy? | 7 points
JCT Order of Precedence * Contract Agreement overrides all. * Conditions of Contract follow. * Specifications next. * Drawings last; must comply with higher-priority documents.
53
When do you become a contract administrator? | and duties
* CA role formally begins once contract is executed * Pre-contract services (tender prep, procurement advice) may be agreed but not formal CA role
54
What duties change once you’re formally the CA vs pre-contract advisor? | Pre vs Post
* Pre-contract (advisor): procurement advice, tender docs, tender reports, draft contract → client advocate. * Post-contract (CA): certify impartially, issue instructions, value works, EoT/PC, defects → neutral administrator.
55
What’s the risk to your client if you act unfairly as CA? | 6 points
* Legal disputes and claims from contractor. * Financial loss from overpayments or penalties. * Delays due to disagreements or adjudication.
56
What is a vesting certificate, and why is it important for off-site materials | 3 points
* Confirms transfer of property ownership from seller to buyer. *Protects employer if contractor insolvent (materials can’t be claimed by creditors)
57
Two types of provisional sums? | 4 points
* Defined S: Scope, location, or specification is partially known * Undefined PS: Scope or details are uncertain or unknown.
58
What is a CVI? | 4 points
* Confirmation of Verbal Instruction * Not formally recognised under JCT * Must be followed up with written instruction to be binding
59
What risks arise if you rely only on CVIs without following up formally | 3 points
* No legal proof of instructions; hard to enforce * Risk of non-payment disputes * Programme/EoT disputes * No audit trail → harder to defend in adjudication
60
What is best practice process around CVIs to show control and professionalism? | 5 points
* Record verbal instruction in site minutes * Issue CVI form as temporary note * CA issues formal written instruction (AI/CAI/CE) * Maintain audit trail
61
Who is responsible for final account? | 3 points and what it covers
* CA responsible for preparing/agreement of final account * Covers: variations, PS adjustments, loss & expense, fluctuations * Contractor submits info, but CA certifies * CA issues Final Certificate
62
When should the final account be agreed?
* Contractor submits info → within 6 months of PC * CA/QS issues Final Certificate → within 3 months of receipt
63
Information required to agree final account? | 7 points
* Measured work: Quantities of completed work. * Variations: * Provisional sums: * Adjustments:
64
Types of procurement methods?
* Traditional: Design by client/architect, then tender to contractor. * Design & Build: Contractor responsible for design and construction. * Management - Employer contracts directly with trade contractors — maximum control, employer takes risk.
65
What is the traditional procurement method? | advantages and disadvantages
* Client provides design via architect/engineer. * Contractor builds based on completed design. * Tendered competitively for price. * Separation of design and construction responsibilities.
66
What is the D&B procurement method?
* Contractor handles design and construction. * Client provides brief, not detailed design. * Single contract for design, build, and sometimes commissioning. * Can reduce client risk but less design control.
67
What is a single-stage tender?
* Contractor submits full priced bid based on complete design. * Awarded after one round of bidding. * Suitable for straightforward projects with clear specifications.
68
What is a negotiated tender?
* Contractor is selected directly without competitive bidding. * Price and terms are discussed and agreed with the client. * Often used for specialist work or trusted contractors. * Can be faster but less competitive than open tendering.
69
How did you calculate the level of LAD’s | 4 points
* Fixed daily/weekly rate in Contract Particulars * Genuine pre-estimate of likely loss (not a penalty) * Based on finance costs, lost rent/income, extended fees, temporary costs
70
When can a MW be used? | 4 points
* MW = simple, low-value, low-complexity works. * Examples: refurbishments, extensions, maintenance. * Design by employer/consultants (unless MWCD used). * Not for complex phasing or nominated subcontractors.
71
What are the Notice Requirement for Delayed Completion
* Delay must be formally notified in writing Should include: * Cause of delay * Likely effect on completion * Triggers CA’s duty to consider an EOT
72
EOT Process
1. Contractor issues delay notice 2. CA reviews cause and impact 3. CA makes a fair and reasonable assessment 4. EOT granted (or refused) in writing 5. Completion Date adjusted if granted
73
Why should you Issue an EOT prior to completion date
* EOTs should be issued as soon as delay is apparent * Avoids uncertainty and improper use of LADs * Good contract administration practice
74
Liquidated and Ascertained Damages (LADs)
* Pre-agreed daily/weekly sum for delay Employer must: * Issue NCC * Apply LADs strictly in accordance with contract
75
Impact of EOT on LADs
* Valid EOT pushes back Completion Date * LADs only apply after revised Completion Date * Prevents Employer benefiting from own delay (prevention principle)
76
Benefits of Formal Documentation
* Clear audit trail * Reduces disputes * Protects CA and Employer * Demonstrates compliance with contract and RICS professionalism
77
Why Traditional Tender (NHSPS)
* NHSPS require 3 quotes for works that exceed £5,000 as standard policy
78
Requirements/Process when Selecting Contractors (NHS Projects)
* Constructionline Gold accreditation * Approved IW / specialist contractor * NHSPS may nominate contractors for tender * Relevant experience
79
Chesterton HC - What checks do you carry out during a tender analysis?
* Check for arithmetical errors * Review completeness of submission * Assess programme and lead-in times * Compare cost breakdowns * Review quality and compliance with specification
80
Chesterton HC - How do you advise a client on contractor selection?
Provide a tender report and compare: * Cost * Programme * Quality * Risks Recommend most economically advantageous tender
81
Shoebury HC -What happens when you issue Practical Completion?
* Start of Rectification Period * Release of half retention (typically 2.5%) * End of liquidated damages liability * Transfer of possession to client
82
Shoebury HC - What is Practical Completion?
* Works are substantially complete * Only minor defects/snags remain * Building can be used for its intended purpose
83
Shoebury HC - What would stop you issuing Practical Completion?
* Significant incomplete works * Health and safety risks * Building not usable * Major defects present
84
20 TW - Why did you grant the EOT?
* Delay caused by client variations * Contractor not at fault * Falls under relevant event
85
What is 'Time at Large' -
* No fixed completion date * Employer breaches or delays * Contractor must complete in reasonable time * Client cannot apply LADs
86
Histon - Why did the variation lead to an EOT?
* Additional works increased programme duration * Contractor not responsible for delay * Loss and expense can be claimed
87
What is the JCT Extension of Time (EOT) clause?
* Under JCT Minor Works Building Contract 2016, the EOT clause is Clause 2.3
88
JCT 2024 payment cycle
Day 0 → Interim Valuation Day 7 → Due date - Payment becomes “due” Day 12 → Last date for CA to issue Payment Cert Day 16 → Last chance for a Pay Less Notice Day 21 → Final date for Payment